Sunday, July 31, 2011

STATE OF RAJASTHAN & ANR. v. J.K. SYNTHETICS LTD. & ANR. [2011] INSC 565 (4 July 2011)

Judgement
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 4927 OF 2011 [Arising out of SLP [C] No.15621/2007]

State of Rajasthan & Anr. ... Appellants
V/s.
J.K.Synthetics Ltd. & Anr. ... Respondents

WITH
C.A. No. 4928 of 2011 (Arising out of SLP [C] No.15259/2007);
C.A. No. 4929 of 2011 (Arising out of SLP [C] No.15260/2007);

C.A. No. 4931 of 2011 (Arising out of SLP [C] No.15407/2007);

C.A. No. 4930 of 2011 (Arising out of SLP [C] No.15873/2007), and C.A. No. 4932 of 2011 (Arising out of SLP [C] No.6417/2010).


R.V.RAVEENDRAN, J.

Leave granted.


2. In these appeals by special leave, the appellants challenge the orders of the Division Bench of the Rajasthan High Court, dismissing its appeals against a common order of the learned Single Judge, restricting the interest 2 on arrears of royalty to 12% per annum, instead of 24% per annum demanded by the State of Rajasthan.

3. The first respondent in each of these appeals is or was the holder of a mining lease for limestone. Section 9 of the Mines and Minerals (Development and Regulation) Act, 1957 (`Act' for short) deals with Royalties in respect of mining leases. Sub-section (2) thereof requires the holder of a mining lease to pay royalty in respect of any mineral removed or consumed by him from the leased area at the rate for the time being specified in the Second Schedule to the Act, in respect of that mineral. Sub- section (3) thereof empowers the Central Government, by notification published in the official gazette, to amend the Second Schedule so as to enhance the rates at which royalty shall be payable in respect of any mineral with effect from such date as may be specified in the notification.

4. By notification dated 5.5.1987, the Central Government had amended the Second Schedule to the Act and increased the royalty in respect of (limestone) from Rs.4.50 per tonne to Rs.10 per tonne. By a subsequent notification dated 17.2.1992, the Second Schedule to the Act was again 3 amended and the rate or royalty for limestone was increased from Rs.10/- per tonne to Rs.25/- per tonne.

5. The respective first respondent in these appeals (together referred to the `contesting respondents') filed writ petitions challenging the constitutional validity of section 9(3) of the Act and the notification dated 17.2.1992 increasing the rate of royalty from Rs.10 to Rs.25 per tonne. In all the cases (except in the case of J. K. Udaipur Udyog Ltd), the High Court issued interim orders directing the state government not to take coercive steps to recover royalty at the rate of Rs.25 per metric tonne in pursuance of notification dated 17.2.1992, subject to the writ petitioners paying royalty at the rate of Rs.10 per MT and furnishing bank guarantee for the difference of Rs.15 per MT. In the case of J. K. Udaipur Udyog Ltd, the High Court made an interim order as in the other cases, with an additional condition that in case the said writ petitioner ultimately failed in the writ petition, the difference amount due from the writ petitioner shall be recovered with interest at the rate of 18% per annum.

6. Ultimately, the several writ petitions filed by the contesting respondents challenging the section 9(3) of the Act and the notification dated 17.2.1992 increasing the royalty, were dismissed in the year 1996 following 4 the decision of this Court in State of Madhya Pradesh vs. Mahalaxmi Fabric Mills Ltd.,- 1995 Supp (1) SCC 642, wherein this Court had upheld the validity of section 9(3) of the Act and the notification revising the rate of royalty. As a consequence of such dismissal, each of the contesting respondents claims to have paid the difference in royalty (that is at the rate of Rs.15/- per MT) in the years 1996-1997.

7. Rule 64-A of the Minerals Concession Rules, 1960 (`Rules' for short) provides for levy of interest on arrears of royalty and other dues and the same is extracted below : "64-A. The State Government may, without prejudice to the provisions contained in the Act or any other rule in these rules, charge simple interest at the rate of 24% per annum on any rent, royalty or fee, other than the fee payable under sub-rule (1) of Rule 54, or other sum due to that government under the Act or these rules or under the terms and conditions of any prospecting licence or mining lease from the sixtieth day of the expiry of the date fixed by that government for payment of such royalty, rent, fee or other sum and until payment of such royalty, rent, fee or other sum is made."

8. The State of Rajasthan issued the following demand notices to the contesting respondents calling upon them to pay interest at the rate of 24% per annum under Rule 64-A of the Rules, on the difference in royalty which had been withheld on account of the interim orders obtained by them and which were belatedly paid, after rejection of their writ petitions : 5 SNo. Name of Lessee Writ Petition Interest Date of Demand Number (where stay Demanded was obtained) (in Rupees)

1. J. K. Synthetic Ltd WP No. 5721/1992. 6,98,54,031 6.11.1997

2. Birla Corporation Ltd. WP No. 6008/1992 5,99,81,784 24.7.1997

3. J. K. Udaipur Udyog Ltd. WP No. 3871/1993 1,12,76,364 12.3.1997

4. J. K. Synthetic Ltd WP No. 5300/1992. 20,04,474 24.7.1997

5. J. K. Corporation Ltd WP No. 5202/1992. 1,83,10,418 4.11.1996

6. Shree Cement Ltd. WP No. 5004/1992 2,91,89,622 21.1.1997

9. The contesting respondents at this stage again filed a second round of writ petitions challenging the notices demanding interest, contending that they were not liable to pay interest. They also challenged the validity of Rule 64-A of the Rules. During the pendency of those petitions, this Court in South Eastern Coalfields Ltd. vs. State of M.P. - 2003 (8) SCC 648, upheld the validity of Rule 64A. On the peculiar facts of that case which were noticed in para 30 of the said judgment, this Court held that it will not interfere, in exercise of the jurisdiction under Article 136 of the Constitution of India, the discretion exercised by the High Court in reducing the rate of interest from 24% per annum to 12% per annum making it clear that the same shall not however be treated as precedent in any other case. After the said decision, what remained to be considered in the writ petitions filed by the contesting respondent was the rate of interest. The contesting respondents as writ petitioners submitted before the learned Single Judge that the claim for interest at 24% per annum was harsh, excessive and 6 inequitable, and interest should not be charged at a rate higher than 9% per annum. They relied upon the decision of this court in Saurashtra Cement and Chemical Industries Ltd., vs. Union of India - 2001 (1) SCC 91, where this court had reduced the rate of interest on unpaid royalty imposed by the High Court (18% per annum) to 9% per annum. The learned Single Judge allowed the writ petitions of the six contesting respondents in part, by common order dated 11.8.2005. He noted that the Advocate General had submitted that the State Government was entitled to interest at 18% per annum. The learned Single Judge noted that the trend of directions by the Supreme Court showed that State should get interest at least at the rate of 12% per annum on the delayed payments. Consequently, he upheld the demand for interest only to an extent of 12% per annum and set aside the demand for the interest at the higher rate of 24% per annum, with a condition that if interest at 12% per annum on the delayed payments was not paid within three months, the respective writ petitioners shall be liable to pay interest at 24% per annum. It is stated by the contesting respondents that all of them have paid the interest at the rate of 12% per annum on the delayed payments, within three months period. Be that as it may. 7

10. The state government filed intra-court appeals challenging the order of the learned Single Judge. A Division Bench of the High Court has dismissed those appeals by the impugned orders dated 14.11.2009, 13.11.2006, 13.11.2006, 13.3.2007, 14.11.2006 and 4.11.2009, on the ground that the order of the learned Single Judge was based on an admission/concession by the learned Advocate General and therefore, the order did not call for interference. The said orders are challenged in these appeals by special leave by the state government.

11. On the contentions raised, the following questions arise for consideration : (i) Whether the Advocate General appearing for the State had consented to award of interest at 12% per annum? (ii) When the High Court grants an interim stay of a demand for payment of money, in a writ petition challenging the levy which is ultimately dismissed, without any specific direction for payment of interest, whether the respondent can claim interest on the amount due for the period covered by the interim order? (iii) Whether Rule 64-A vests any discretion in the state government to charge interest at a rate less than 24% per annum in appropriate or deserving cases? (iv) Whether the rate of interest awarded at 12% per annum requires to be increased? 8 Re : Question (i)

12. The first question is whether the order of the learned Single Judge is based on any consent and whether the learned Advocate General appearing for the state had conceded that the state government is entitled to interest at only 12% per annum. We extract below the relevant portion of the order of the learned Single Judge, where there is a reference to the submission made of the learned Advocate General : "On the other hand, the learned Advocate General submits that the state government is entitled for the rate of interest @ 18% per annum but even looking to the present trend of Hon'ble Supreme Court, Government must at least get interest @12% per annum on the delayed payment of the difference royalty amount as has been awarded by the Hon'ble Supreme Court in South Easter Coalfields case (supra). Having heard the learned (counsel) for the parties, I am of the view that in the facts and circumstances of the present case, the demand of interest @ 12% per annum would meet the ends of justice in the light of the Apex Court judgement in South Eastern Coalfields case (supra)." The only submission of the Advocate General before the learned Single Judge was that the State Government was entitled to interest at the rate of 18% per annum. The further observation that as per the trend of Supreme Court decision, the state government should get interest at least at the rate of 12% per annum on the delayed payments, as awarded in the decision in South Eastern Coalfields, is an observation of the learned Single Judge, and not a concession by the learned Advocate General. Further, subsequent para 9 of the order of the learned Single Judge makes it clear beyond doubt that the order was not on consent or concession, but is made on merits following the decision of this Court in South Eastern Coalfields. Therefore, the assumption by the Division Bench of the High Court that the learned Advocate General had made a concession and the order of the learned Single Judge was a consent order and therefore, it was not open for the State Government to challenge the order of the learned Single Judge, is obviously erroneous. The order of the Division Bench cannot therefore be sustained.

13. Even if it is assumed that the learned Advocate General had submitted that "looking to the present trend of the decision of Supreme Court", Government should at least get interest at the rate 12% per annum on the delayed payment of difference in royalty amount as had been awarded in South Eastern Coalfields, that would neither be an admission nor a concession that the state government is entitled to interest only at the rate of 12% per annum in regard to the rate of interest. It would be nothing more than a statement made with reference to the decision in South Eastern Coalfields and such a statement would not come in the way of order being challenged if the state government is of the view that it is entitled to get a higher rate of interest. 10 Re : Question (ii)

14. The contesting respondents filed the second round of writ petitions before the High Court challenging the demand for interest and the validity of Rule 64A, on two grounds : that Rule 64-A was invalid; that the rate of interest was excessive. The learned Single Judge negatived the first contention in view of the decision of this South Eastern Coalfields. He however accepted the second contention and restricted the rate of interest to 12% per annum. The contesting respondents have not challenged the order of the High Court holding that they are liable to pay interest at 12% per annum. They have in fact paid the interest at such rate. Before us, one of the contentions urged to resist the claim of the State for increase in the rate of interest, is with reference to the fundamental question about the liability itself. It was submitted that they were not liable to pay interest on the increase in royalty amount, in view of their challenge to the increase and order of interim stay of the High Court. It was submitted by the contesting respondents, that even if the writ petitions challenging the notification dated 17.2.1992 revising the royalty rate were ultimately dismissed, in the absence of any specific direction by the High Court to pay interest on the difference in royalty amount, they were not liable to pay any interest during the period of operation of stay. This question is no longer res integra. We may refer to 11 the decisions of this Court that have categorically laid down about the liability to pay interest for the period of stay when the stay is ultimately vacated.

15. In Kanoria Chemicals and Industries Ltd. vs. UP State Electricity Board - 1997 (5) SCC 772, this Court held that grant of stay of a notification revising the electricity charges does not have the effect of relieving the consumer of its obligation to pay interest (or late payment surcharge) on the amount withheld by them by reason of the interim stay, if and when the writ petitions are dismissed ultimately. The said principle was based on the following reasoning : "Holding otherwise would mean that even though the Electricity Board, which was the respondent in the writ petitions succeeded therein, is yet deprived of the late payment surcharge which is due to it under the tariff rules/regulations. It would be a case where the Board suffers prejudice on account of the orders of the court and for no fault of its. It succeeds in the writ petition and yet loses. The consumer files the writ petition, obtains stay of operation of the Notification revising the rates and fails in his attack upon the validity of the Notification and yet he is relieved of the obligation to pay the late payment surcharge for the period of stay, which he is liable to pay according to the statutory terms and conditions of supply - which terms and conditions indeed form part of the contract of supply entered into by him with the Board. We do not think that any such unfair and inequitable proposition can be sustained in law.......

It is equally well settled that an order of stay granted pending disposal of a writ petition/suit or other proceeding comes to an end with the dismissal of the substantive proceeding and that it is the duty of the court in such a case to put the parties in the same position they would have been but for the interim orders of the court. Any other view would result in the act or order of the court prejudicing a party (Board in this case) for no fault of its and 12 would also mean rewarding a writ petitioner in spite of his failure. We do not think that any such unjust consequence can be countenanced by the courts. As a matter of fact, the contention of the consumers herein, extended logically should mean that even the enhanced rates are also not payable for the period covered by the order of stay because the operation of the very notification revising/enhancing the tariff rates was stayed. Mercifully, no such argument was urged by the appellants. It is ununderstandable how the enhanced rates can be said to be payable but not the late payment surcharge thereon, when both the enhancement and the late payment surcharge are provided by the same Notification - the operation of which was stayed."

(emphasis supplied) The above principles have been followed and reiterated by this Court in Rajasthan Housing Board vs. Krishna Kumari - 2005 (13) SCC 151 and Nav Bharat Ferro Allays Ltd vs. Transmission Corporation of Andhra Pradesh Ltd - 2011 (1) SCC 216.

16. The same question was considered by this Court, when examining the constitutional validity of Rule 64-A in South Eastern Coalfields. This Court held that Rule 64-A providing for payment of interest at the rate of 24% per annum, was valid. In that case also, it was contended before this Court that non-payment of the increased amount of royalty was protected by the interim orders of the High Court and therefore, they should not be held liable for payment of interest so long as the money was withheld under the protective umbrella of the interim orders. It was further contended that merely because the writ petition was finally dismissed, it does not follow 13 that the interim order becomes vitiated or erroneous, as it may still be a perfectly justified interim order. It was further argued that as they had shown their bona fides by paying the difference in royalty immediately after the validity of the notification dated 17.2.1992 was upheld, they could not be made liable to pay interest. All these contentions were rejected by this Court on the ground that the principle of restitution was a complete answer to the said submissions. This Court held : "The principle of restitution has been statutorily recognized in Section 144 of the Code of Civil Procedure, 1908. Section 144 of the CPC speaks not only of a decree being varied, reversed, set aside or modified but also includes an order on par with a decree. The scope of the provision is wide enough so as to include therein almost all the kinds of variation, reversal, setting aside or modification of a decree or order. The interim order passed by the Court merges into a final decision. The validity of an interim order, passed in favour of a party, stands reversed in the event of final decision going against the party successful at the interim stage. Unless otherwise ordered by the Court, the successful party at the end would be justified with all expediency in demanding compensation and being placed in the same situation in which it would have been if the interim order would not have been passed against it. The successful party can demand (a) the delivery of benefit earned by the opposite party under the interim order of the court, or (b) to make restitution for what it has lost; and it is the duty of the court to do so unless it feels that in the facts and on the circumstances of the case, the restitution would far from meeting the ends of justice, would rather defeat the same. Undoing the effect of an interim order by resorting to principles of restitution is an obligation of the party, who has gained by the interim order of the Court, so as to wipe out the effect of the interim order passed which, in view of the reasoning adopted by the court at the stage of final decision, the court earlier would not or ought not to have passed. There is nothing, wrong in an effort being made to restore the parties to the same position in which they would have been if the interim order would not have existed."

14

17. It is therefore evident that whenever there is an interim order of stay in regard to any revision in rate or tariff, unless the order granting interim stay or the final order dismissing the writ petition specifies otherwise, on the dismissal of the writ petition or vacation of the interim order, the beneficiary of the interim order shall have to pay interest on the amount withheld or not paid by virtue of the interim order. Where the statute or contract specifies the rate of interest, usually interest will have to be paid at such rate. Even where there is no statutory or contractual provision for payment of interest, the court will have to direct the payment of interest at a reasonable rate, by way of restitution, while vacating the order of interim stay, or dismissing the writ petition, unless there are special reasons for not doing so. Any other interpretation would encourage unscrupulous debtors to file writ petitions challenging the revision in tariffs/rates and make attempts to obtain interim orders of stay. If the obligation to make restitution by paying appropriate interest on the withheld amount is not strictly enforced, the loser will end up with a financial benefit by resorting to unjust litigation and winner will end up as the loser financially for no fault of his. Be that as it may. 15 Re : Question (iii)

18. The contesting respondents contended that Rule 64A provides that the state government "may" charge simple interest at the rate of 24% per annum; that this being an enabling provision, there is no `mandate' or compulsion to charge interest at 24% per annum; and that therefore, the state government has the discretion to charge interest at a rate lesser than 24% in appropriate deserving cases. It is submitted that if the legislative intent was to provide for interest at the rate of 24% per annum in all cases of delayed payment of royalty/rent/fees without exception, the rule would have been differently worded, and read as follows : "wherever any rent, royalty or fee or other sum due to the government under the Act or the rules or under any prospecting licence or mining lease, is not paid by the due date, the lessee or licensee shall pay interest on the delayed payment at the rate of 24% per annum". It is submitted by the respondents that the word "may" used in the Rule, should be read as vesting a discretion in the government to charge interest or not to charge interest, and if interest is to be charged, at any rate not exceeding 24% per annum.

19. A careful reading of the Rules makes it clear that no such discretion is given to the state government in regard to rate of interest. This will be 16 evident from a combined reading of Rules 31 and 27 and the terms of the statutory form of lease deed (Form K), with Rule 64A. Rule 31 provides that where, an order has been made for the grant of a mining lease, a lease deed in Form K (or in a form as near thereto as circumstances of each case may require), shall be executed. Rule 27 specifies that every mining lease shall be subject to the conditions mentioned therein. Clause (5) of Rule 27 refers to determination : "(5). If the lessee makes any default in the payment of royalty as required under section 9 or payment of dead rent as required under section 9A or commits a breach of any of the conditions specified in sub-rules (1), (2) and (3), except the condition referred to in clause (f) of sub-rule (1), the state government shall give notice to the lessee requiring him to pay the royalty or dead rent or remedy the breach, as the case may be, within sixty days from the date of the receipt of the notice and if the royalty or dead rent is not paid or the breach is not remedied within the said period, the state government may, without prejudice to any other proceedings that may be taken against him, determine the lease and forfeit the whole or part of the security deposit."

The above provision is accordingly incorporated in clause (2) of Part IX of the standard form of lease (Form K).

20. The rate of interest at 24% was substituted in clause (3) of Part VI of the standard form of lease, by the very same amendment which substituted the said percentage in Rule 64A namely, GSR 129 (E) dated 20.2.1991. The words "may charge simple interest" in Rule 64A should be 17 read in the context of the words "without prejudice to the provisions of the Act or any other Rule in these Rules". As noticed above, Rule 45(iv) requires the lease deed to contain a condition that if there is any default in the payment of royalty, the lessor without prejudice to any proceeding that may be taken against the lessee, determine the lease. Therefore, the word "may" used with reference to the words "charge simple interest at the rate of 24% per annum" when read with the words "without prejudice to the provisions contained in the Act or any other Rule", occurring in Rule 64A, make it clear that whenever rent/royalty/fee becomes due, the lessor has several options by way of remedy. The lessor may determine the lease, if the breach is not rectified, even after sixty days' notice to rectify the breach. Alternatively, instead of determining the lease, the rule gives the choice to charge interest at 24% per annum on the amounts due. The third alternative for the state government is to determine the lease and also charge interest at 24% per annum on the outstanding dues. The word `may' is used in Rule 64- A not in the context of giving discretion in regard to rate of interest to be charged, but to give an option or choice to the State Government as to whether it should determine the lease, or charge interest at 24% per annum, or do both. Therefore, where the lease is not determined as a consequence of the default, the State will have to charge interest at 24% per annum on the 18 outstanding amount. If Rule 64A is to be interpreted as giving any discretion, that too unguided discretion, to the authorities to charge any rate of interest, as it would result in misuse and abuse. In this view of the matter, the contentions urged by the parties as to whether the word "may" should be read as "must" or "shall", and, if so, in what circumstances, do not arise for consideration at all.

21. There is also other material in the Rules itself to show that the rate of interest mentioned in Rule 64A was not intended to be flexible and that the rate of interest mentioned therein has to be applied in all cases of non- payment/default. When Rule 64A was amended by notification dated 20.2.1991, increasing the rate of interest to 24% per annum, clause (3) of Part IV of the standard form of lease (Form K) was also amended increasing the rate of interest payable on all dues as 24% per annum. We extract below clause (3) of Part VI of Form K for ready reference : "3. Should any rent, royalty or other sums due to the State Government under the terms and conditions of these presents be not paid by the lessee/lessees within the prescribed time, the same, together with simple interest due thereon at the rate of twenty four per cent per annum may be recovered on a certificate of such officer as may be specified by the State Government by general or special order, in the same manner as an arrears of land revenue."

19 The said clause in Form K makes it clear that the rate of interest should be 24% per annum and there is no discretions in the state government to charge interest at any lesser rate.

22. It is true that annual interest at 24% per annum appears to be marginally higher than the standard market lending rate of interest. But it is not penal in nature. Revenue from mining constitutes one of the major sources of non-tax revenue of the State Governments. Mining lessees are expected to pay the mining dues promptly and without default. If a lesser rate of interest is provided under the Rules, it may lead to unscrupulous lessees indulging in delaying tactics. The intention of Rule 64A is to discourage practices that may be detrimental to recovery of revenue, by providing for a higher rate of interest. Hence, once the State Government chooses not to take the path of determining the lease, charging of interest at 24% is mandatory and leaves no discretion in the State Government in regard to rate of interest.

Re : Question (iv)

23. This brings us to the last question as to what should be the rate of interest. We have seen that Rule 64-A categorically provides that where a mining lessee who is liable to pay rent or any other dues, fails to pay the 20 same, the state government will be entitled to charge simple interest thereon at 24% per annum. The validity of this rule has been upheld by this Court in South Eastern Coalfields. Therefore interest on all delayed payments should be 24% per annum.

24. The contesting respondents submitted that even if the rate of interest under Rule 64-A is 24% per annum, when the liability (on account of increase in Royalty) is under challenge and the matter is pending in court and there is an interim stay of the increase, the liability to pay interest will be within the discretion of the court and court can award a lesser rate. They relied upon the decisions of this Court in Saurashtra Cement (supra) and the decision in South Eastern Coalfields, that the interest should not be more than 9% or 12% per annum, for the period when the stay was in operation.

25. In South Eastern Coalfields which upheld the validity of Rule 64-A, this Court did not interfere with the decision of the High Court awarding interest at 12% per annum, on the following reasoning : "So far as the appeal filed by the State of Madhya Pradesh seeking substitution of rate of interest by 24% per annum in place of 12% per annum as awarded by the High Court is concerned, we are not inclined to grant that relief in exercise of our discretionary jurisdiction under Article 136 of the Constitution especially in view of the opinion formed by the High Court in the impugned decision. The litigation has lasted for a long 21 period of time. Multiple commercial transactions have taken place and much time has been lost in between. The commercial rates of interest (including bank rates) have undergone substantial variations and for quite sometime the bank rate of interest has been below 12%. The High Court has, therefore, rightly (and reasonably) opined that upholding entitlement to payment of interest at the rate of 24% per annum would be excessive and it would meet the ends of justice if the rate of interest is reduced from 24% per annum to 12% per annum on the facts and in the circumstances of the case. We are not inclined to interfere with that view of the High Court but make it clear that this concession is confined to the facts of this case and to the parties herein and shall not be construed as a precedent for overriding Rule 64A of the Mineral Concession Rules, 1960. It is also clarified that the payment of dues should be cleared within six weeks from today (if not already cleared) to get the benefit of reduced rate of interest of 12%; failing the payment in six weeks from today the liability to pay interest @24% per annum shall stand."

(emphasis supplied) Therefore, it is clear that the concession extended in that case by permitting interest only at 12% per annum was confined to the facts of that case and to the parties therein and is not be treated as a precedent, for nullifying or overriding Rule 64-A of the Rules.

26. In Saurashtra Cement, while dismissing the appeals challenging the validity of the increase in royalty following the decision in Mahalaxmi Fabric Mills (Supra), this Court dealt with a case, where the High Court had granted interim stay of the notification regarding increase in royalty but however while vacating the interim order and discharging the rule, had directed the payment of interest at 18% per annum. Pattanaik J., (as he then 22 was) in the last line of his order reduced the rate of interest to 9% per annum without assigning any specific reason, except observing that 18% was unreasonable. In his concurring judgment, Banerjee J., observed as under : "The imposition of 18% interest with yearly rests cannot in our view find support in the contextual facts since the validity of the legislation itself is in question before this Court. The payment of interest being in the discretion of the court, we, therefore, do not wish to interfere with the award of interest, as such though the rate at which it has been awarded needs some modification in the contextual facts and as such we direct that the rate of interest be 9% simple interest and not as directed by the High Court."

(emphasis supplied) A careful reading of the said judgment shows that while deciding the issue of interest, this Court had overlooked Rule 64-A which is a statutory provision entitling the government to claim interest at 24% per annum. This Court apparently proceeded on the basis that there was no statutory or contractual provision for the payment of interest, and therefore, question of interest was wholly within the discretion of the court. Therefore, the said decision may not also be of any assistance.

27. We find that the decision in Kanoria Chemicals (supra) throws considerable light on the logic behind court's discretion in awarding interest in such cases. That case, as noticed earlier, dealt with increase in electricity charges. The relevant provision specifically provided that in regard to 23 delayed payments of the bills, the consumer shall pay additional charge per day of seven paisa per hundred rupees on the unpaid amount of the bill, which works out to 25.55% per annum. This Court reduced the same to 18% per annum on the following reasoning : "Sri Vaidyanathan then contended that the rate of "late payment surcharge" provided by clause 7(b) is really penal in nature inasmuch as it works out to 25.5 per cent per annum. The learned counsel also submitted that the petitioners understood the decision in Adoni Ginning as relieving them of their obligation to pay interest for the period covered by the interim order and that since they were acting bona fide they should not be mulcted with such high rate of interest. We cannot agree that the rate of late payment surcharge provided by clause 7(b) is penal, but having regard to the particular facts and circumstances of this case and having regard to the fact that petitioners could possibly have understood the decision in Adoni Ginning as relieving them of their obligation to pay interest/late payment surcharge for the period of stay, we reduce the rate of late payment surcharge payable under clause 7(b) to eighteen per cent. But this direction is confined only to the period covered by the stay orders in writ petitions filed challenging the notification dated 21.4.1990 and limited to 1.3.1993 the date on which those writ petitions were dismissed." (emphasis supplied) Therefore, whenever there is a challenge to a levy or challenge to an increase in the tariff or rates, and an order of interim stay of recovery is made in the said writ proceedings and the writ petition is ultimately rejected, the court should invariably award interest by way of restitution. Where the statute or contract prescribed a specific rate of interest, the court should normally adopt such rate while awarding interest, except where the court 24 proposes to award a higher or lower rate of interest, for special and exceptional reasons.

28. Let us consider whether there are any special or exceptional circumstances for reducing the statutory interest in this case. In the case of one of the contesting respondents (J. K. Udaipur Udyog Ltd.), there was a categorical direction while granting interim stay that in the event of failure in the writ petition the writ petitioner will have to pay interest at the rate of 18% per annum. That was a condition of interim order and therefore, it is possible that the parties bona fide proceeded on the basis that interest will be only 18% per annum. In the writ petitions of other contesting respondents, there was no such condition regarding interest while granting the stay. But as pointed out in Kanoria Chemicals, it is possible that the contesting respondents thought, by reason of the fact that there was no condition for payment of interest while granting stay, they may not be required to pay the statutory rate of interest. More importantly, the learned Advocate General appearing for the State had made a submission before the learned Single Judge that state government was entitled to interest only at the rate of 18% per annum. In the peculiar and special circumstances of these cases, we are of the view that the appellants will be entitled to interest at 18% per annum 25 in respect of royalty that became due between 17.2.1992 and the date of dismissal of their respective writ petitions. For the period subsequent to the dismissal of the writ petitions, the contesting respondents will be liable to pay interest on the said amount, at the rate of 24% per annum till date of payment.

29. The contesting respondent in the last case (Shree Cement) raised an additional contention. It was submitted that clause VI(iii) of the Lease Deed in its case provided that any royalty which was not paid within the prescribed time shall be paid with simple interest at the rate of 10% per annum. It is therefore contended that the interest on any arrears cannot be more than 10% per annum in its case. The lease is governed by the Minerals and Concessions Rules 1960 and execution of the lease deed is itself is in compliance with one of the requirement of the rules, namely Rule 31. Once Rule 64A was amended by notification dated 20.2.1991 increasing the rate of interest to 24% per annum, any term in the lease deed prescribing a lesser rate of interest, shall have to yield to Rule 64-A from that date as the rule will prevail over the terms of the lease. This position is evident from the decision in South-Eastern Coalfields also. 26 Conclusion

30. In view of the above, we allow these appeals in part and modify the rate of interest in each case as under :

(i) from 17.2.1992 to the date of dismissal of the respective writ petition (challenging the notification dated 17.2.1992), the rate of interest shall be 18% per annum on the arrears of royalty etc.; and (ii) from the date of dismissal of the writ petition till date of payment, the rate of interest shall be 24% per annum. .................................J.

(R V Raveendran)
................................J.

(P. Sathasivam)
New Delhi;

STATE OF ORISSA & ORS. v. BHAGYADHAR DASH [2011] INSC 564 (4 July 2011)

Judgement
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO.4933 OF 2011 [Arising out of SLP [C] No.20318/2008]

State of Orissa & Ors. ... Appellants
V/s.
Bhagyadhar Dash ... Respondent

WITH With CA No. 4935 of 2011 (@ SLP [C] No.23251/2008) With CA No. 4936 of 2011 (@ SLP [C] No.23252/2008) With CA No. 4934 of 2011 (@ SLP [C] No.23346/2008) With CA No. 4937 of 2011 (@ SLP [C] No.26639/2008) With CA No. 4939 of 2011 (@ SLP [C] No.27116/2008) With CA No. 4940 of 2011 (@ SLP [C] No.27386/2008) With CA No. 4941 of 2011 (@ SLP [C] No.27387/2008) With CA No. 4942 of 2011 (@ SLP [C] No.27388/2008) With CA No. 4943 of 2011 (@ SLP [C] No.7099/2009) With CA No. 4944 of 2011 (@ SLP [C] No.31702/2010) With CA No. 4945 of 2011 (@ SLP [C] No.32048/2010) With CA No. 4946 of 2011 (@ SLP [C] No.33798/2010)
R.V.RAVEENDRAN, J.

Leave granted.

2. These appeals by special leave are by the State of Orissa aggrieved by the orders of the Chief Justice of Orissa High Court allowing the 2 applications filed under Section 11 of the Arbitration and Conciliation Act 1996 (`Act' for short) filed by contractors and appointing arbitrators to decide the disputes raised by them against the State Government. The learned Chief Justice held that the last sentence of the proviso to clause 10 of the conditions of contract (forming part of the agreements between the state and the contractors) is an arbitration agreement. The appellants challenge the said orders on the ground that there is no arbitration agreement and therefore the applications under section 11 of the Act filed by the contractors ought to have been dismissed. Therefore the short question that arises for our consideration in these appeals is whether the said clause is an arbitration agreement. The essentials of an arbitration agreement

3. In K K Modi vs. K N Modi [1998 (3) SCC 573] this court enumerated the following attributes of a valid arbitration agreement :

"(1) The arbitration agreement must contemplate that the decision of the Tribunal will be binding on the parties to the agreement, (2) that the jurisdiction of the Tribunal to decide the rights of parties must derive either from the consent of the parties or from an order of the Court or from a statute, the terms of which make it clear that the process is to be an arbitration, (3) the agreement must contemplate that substantive rights of parties will be determined by the agreed tribunal, 3 (4) that the tribunal will determine the rights of the parties in an impartial and judicial manner, with the tribunal owing an equal obligation of fairness towards both sides, (5) that the agreement of the parties to refer their disputes to the decision of the Tribunal must be intended to be enforceable in law, and lastly, (6) the agreement must contemplate that the tribunal will make a decision upon a dispute which is already formulated at the time when a reference is made to the Tribunal."

Following K.K. Modi and other cases, Bihar State Mineral Development Corporation v. Encon Builders (IP) Ltd. - 2003 (7) SCC 418, this court listed the following as the essential elements of an arbitration agreement:

"(i) There must be a present or a future difference in connection with some contemplated affair;

(ii) There must be the intention of the parties to settle such difference by a private tribunal;

(iii) The parties must agree in writing to be bound by the decision of such tribunal; and (iv) The parties must be ad idem."


4. In Jagdish Chander vs. Ram Chandra [2007 (5) SCC 719], this Court, after referring to the cases on the issue, set out the following principles in regard to what constitutes an arbitration agreement :

"(i) The intention of the parties to enter into an arbitration agreement shall have to be gathered from the terms of the agreement. If the terms of the agreement clearly indicate an intention on the part of the parties to the agreement to refer their disputes to a private tribunal for adjudication and an willingness to be bound by the decision of such tribunal on such disputes, it is arbitration agreement. While there is no specific form of an 4 arbitration agreement, the words used should disclose a determination and obligation to go to arbitration and not merely contemplate the possibility of going for arbitration. Where there is merely a possibility of the parties agreeing to arbitration in future, as contrasted from an obligation to refer disputes to arbitration, there is no valid and binding arbitration agreement.

(ii) Even if the words 'arbitration' and 'arbitral tribunal (or arbitrator)' are not used with reference to the process of settlement or with reference to the private tribunal which has to adjudicate upon the disputes, in a clause relating to settlement of disputes, it does not detract from the clause being an arbitration agreement if it has the attributes or elements of an arbitration agreement. They are : (a) The agreement should be in writing. (b) The parties should have agreed to refer any disputes (present or future) between them to the decision of a private tribunal. (c) The private tribunal should be empowered to adjudicate upon the disputes in an impartial manner, giving due opportunity to the parties to put forth their case before it. (d) The parties should have agreed that the decision of the Private Tribunal in respect of the disputes will be binding on them.

(iii) Where the clause provides that in the event of disputes arising between the parties, the disputes shall be referred to Arbitration, it is an arbitration agreement. Where there is a specific and direct expression of intent to have the disputes settled by arbitration, it is not necessary to set out the attributes of an arbitration agreement to make it an arbitration agreement. But where the clause relating to settlement of disputes, contains words which specifically excludes any of the attributes of an arbitration agreement or contains anything that detracts from an arbitration agreement, it will not be an arbitration agreement. For example, where an agreement requires or permits an authority to decide a claim or dispute without hearing, or requires the authority to act in the interests of only one of the parties, or provides that the decision of the Authority will not be final and binding on the parties, or that if either party is not satisfied with the decision of the Authority, he may file a civil suit seeking relief, it cannot be termed as an arbitration agreement.

(iv) But mere use of the word 'arbitration' or 'arbitrator' in a clause will not make it an arbitration agreement, if it requires or contemplates a further or fresh consent of the parties for reference to arbitration. For example, use of words such as "parties can, if they so desire, refer their disputes to arbitration" or "in the event of any dispute, the parties may also agree to refer the same to arbitration" or "if any disputes arise between the parties, they should consider settlement by arbitration" in a clause relating to settlement of disputes, indicate that the clause is not intended to be an arbitration agreement. Similarly, a clause which states that "if the parties so decide, the disputes shall be referred to arbitration" or "any disputes between parties, if they so agree, shall be referred to arbitration" is not an arbitration agreement. Such clauses merely indicate a desire or hope to 5 have the disputes settled by arbitration, or a tentative arrangement to explore arbitration as a mode of settlement if and when a dispute arises. Such clauses require the parties to arrive at a further agreement to go to arbitration, as and when the disputes arise. Any agreement or clause in an agreement requiring or contemplating a further consent or consensus before a reference to arbitration, is not an arbitration agreement, but an agreement to enter into an arbitration agreement in future."


5. The following passage from Russell on Arbitration (19th Edn. Page 59) throws some light on this issue:

"If it appears from the terms of the agreement by which a matter is submitted to a person's decision, that the intention of the parties was that he should hold an enquiry in the nature of a judicial enquiry and hear the respective cases of the parties and decide upon evidence laid before him, then the case is one of an arbitration. The intention in such case is that there shall be a judicial inquiry worked out in a judicial manner. On the other hand, there are cases in which a person is appointed to ascertain some matter for the purpose of preventing differences from arising, not of setting them when they have arisen".

Cases where the tests were applied to different clauses to find out whether they could be termed as `arbitration agreement' 6. In K.K. Modi, the clause that arose for consideration was as under :

"9. Implementation will be done in consultation with the financial institutions. For all disputes, clarification etc., in respect of implementation of this agreement, the same shall be referred to the Chairman, IFCI or his nominees whose decisions will be final and binding on both the groups".

This Court held that the said clause was not an arbitration agreement on the following reasoning:

"Therefore our Courts have laid emphasis on (1) existence of disputes as against intention to avoid future dispute; (2) the tribunal or forum so chosen is intended to act judicially after taking into account relevant evidence before it and the submissions made by the parties before it; and 6 (3) the decision is intended to bind the parties. Nomenclature used by the parties may not be conclusive.

The purport of Clause 9 is to prevent any further disputes between Groups A and B. Because the agreement requires division of assets in agreed proportions after their valuation by a named body and under a scheme of division by another named body. Clause 9 is intended to clear any other difficulties which may arise in the implementation of the agreement by leaving it to the decision of the Chairman, IFCI. This clause does not contemplate any judicial determination by the Chairman of the IFCI. . . Thus, clause 9 is not intended to be for any different decision than what is already agreed upon between the parties to the dispute. It is meant for proper implementation of the settlement already arrived at. A judicial determination, recording of evidence etc. are not contemplated..."

(emphasis supplied)

7. In State of Uttar Pradesh vs. Tipper Chand - 1980 (2) SCC 341, the following clause fell for consideration:

"Except where otherwise specified in the contract the decision of the Superintending Engineer for the time being shall be final, conclusive and binding on all parties to the contract upon all questions relating to the meaning of the specifications, design, drawing and instructions hereinbefore mentioned. The decision of such Engineer as to the quality of workmanship, or materials used on the work, or as to any other question, claim, right, matter or things whatsoever, in any way arising out of or relating to the contract, designs, drawing specifications, estimates, instructions, orders, or these conditions, or otherwise concerning the works, or the execution or failure to execute the same, whether arising during the progress of the work, or after the completion or abandonment of the contract by the Contractor, shall also be final, conclusive and binding on the Contractor".

The High Court held that the clause was not an arbitration agreement, as it merely conferred power on the Superintending Engineer to take a decision on his own and did not authorise parties to refer any matter to his decision. This court clarified that in the absence of a provision for reference of 7 disputes between parties for settlement, clause merely stating that the "decision of the Superintending Engineer shall be final" was not an arbitration agreement. This Court clarified that an arbitration agreement can either be in express terms or can be inferred or spelt out from the terms of the clause; and that if the purpose of the clause is only to vest in the named Authority, the power of supervision of the execution of the work and administrative control over it from time to time, it is not an arbitration agreement. It also held that the clause did not contain any express arbitration agreement, nor spelt out by implication any arbitration agreement as it did not mention any dispute or reference of such dispute for decision.


8. In State of Orissa vs. Damodar Das [1996 (2) SCC 216], a three Judge Bench of this court considered whether the following clause is an arbitration agreement: "25. Decision of Public Health Engineer to be final.--Except where otherwise specified in this contract, the decision of the public Health Engineer for the time being shall be final, conclusive and binding on all parties to the contract upon all questions relating to the meaning of the specifications; drawings and instructions hereinbefore mentioned and as to the quality of workmanship or material use on the work, or as to any other question, claim, right, matter or thing, whatsoever in any way arising out of, or relating to, the contract, drawings, specifications, estimates, instructions, orders or these conditions, or otherwise concerning the works or the execution of failure to execute the same, whether arising during the progress of the work or after the completion or the sooner determination thereof of the contract".

8 Following the decision in Tipper Chand, this Court held that the said clause did not amount to an arbitration agreement, on the following reasoning:

"It would, thereby, be clear that this Court laid down as a rule that the arbitration agreement must expressly or by implication be spelt out that there is an agreement to refer any dispute or difference for an arbitration and the clause in the contract must contain such an agreement. We are in respectful agreement with the above ratio. It is obvious that for resolution of any dispute or difference arising between two parties to a contract, the agreement must provide expressly or by necessary implication, a reference to an arbitrator named therein or otherwise of any dispute or difference and in its absence it is difficult to spell out existence of such an agreement for reference to an arbitration to resolve the dispute or difference contracted between the parties."

(emphasis supplied)

9. In Bharat Bhushan Bansal vs. Uttar Pradesh Small Industries Corporation Ltd., Kanpur [1999 (2) SCC 166], the following clauses fell for consideration of this Court:

"Decision of the Executive Engineer of the UPSIC to be final on certain matters Except where otherwise specified in the contract, the decision of the Executive Engineer shall be final, conclusive and binding on both the parties to the contract on all questions relating to the meaning, the specification, design, drawings and instructions hereinbefore mentioned, and as to the quality of workmanship or materials used on the work or as to any other question whatsoever in any way arising out of for relating to the designs, drawings, specifications, estimates, instructions, orders or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work, or after the completion thereof or abandonment of the contract by the Contractor shall be final and conclusive and binding on the Contractor.

Decision of the MD of the UPSIC on all other matters shall be final 9 Except as provided in Clause 23 hereof, the decision of the Managing Director of the UPSIC shall be final, conclusive and binding on both the parties to the contract upon all questions relating to any claim, right, matter or thing in any way arising out of or relating to the contract or these conditions or concerning abandonment of the contract by the Contractor and in respect of all other matter arising out of this contract and not specifically mentioned herein".

This Court held that the said clauses did not amount to arbitration agreement on the following reasoning:

"In the present case, reading Clauses 23 and 24 together, it is quite clear that in respect of questions arising from or relating to any claim or right, matter or thing in any way connected with the contract, while the decision of the Executive Engineer is made final and binding in respect of certain types of claims or questions, the decision of the Managing Director is made final and binding in respect of the remaining claims. Both the Executive Engineer as well as the Managing Director are expected to determine the question or claim on the basis of their own investigations and material. Neither of the clauses contemplates a full-fledged arbitration covered by the Arbitration Act".

(emphasis supplied) This Court while noting the distinction between a 'Preventer of disputes' and an 'adjudicator of disputes', observed that the Managing Director under clause 24 of the agreement, was more in the category of an expert who will decide claims, rights, or matters in any way pertaining to the contract and the object of his decision is to avoid disputes and not decide disputes in a quasi-judicial manner. This court also referred to an illustration given in Hudson on 'Building and Engineering Contracts' (11th Edition, Volume II, para 18.067) stating that the following clause was not an arbitration clause and that the duties of the Engineer mentioned therein were administrative and not judicial:

10 "(E)ngineer shall be the exclusive judge upon all matters relating to the construction, incidents and the consequences of these presents, and of the tender specifications, schedule and drawings of the Contract, and in regard to the execution of the works or otherwise arising out of or in connection with the contract, and also as regards all matters of account, including the final balance payable to the contract, and the certificate of the engineer for the time being, given under his hand, shall be binding and conclusive on both parties".


10. We may next refer to the three decisions of this Court relied on by the respondents, where on interpretation, clauses though not described as `arbitration clauses', were held to be arbitration clauses, by applying the tests as to what constitute an arbitration agreement. In Rukmanibai Gupta v. Collector, Jabalpur - 1980 (4) SCC 566, this Court considered whether the following clause amounted to an arbitration agreement :

"15. Whenever any doubt, difference or dispute shall hereafter arise touching the construction of these presents or anything herein contained or any matter or things connected with the said lands or the working or non-working thereof or the amount or payment of any rent or royalty reserved or made payable hereunder the matter in difference shall be decided by the lessor whose decision shall be final".

This Court held that Arbitration agreement is not required to be in any particular form. What is required to be ascertained is whether the parties have agreed that if disputes arise between them in respect of the subject- matter of contract such dispute shall be referred to arbitration; and if the answer was in the affirmative, then such an arrangement would spell out an arbitration agreement. Applying the said test, this court held that the aforesaid clause is an arbitration agreement, as it (a) made a provision for 11 referring any doubt, difference or dispute to a specified authority for decision and (b) it made the "decision" of such authority final. While we respectfully agree with the principle stated, we have our doubts as to whether the clause considered would be an arbitration agreement if the principles mentioned in the said decision and the tests mentioned in the subsequent decision of a larger bench in Damodar Das are applied. Be that as it may. In fact the larger bench in Damodar Das clearly held that the decision in Rukmanibai Gupta was decided on the special wording of the clause considered therein. "The ratio in Rukmanibai Gupta vs. Collector does not assist the respondent. From the language therein this court inferred, by implication, existence of a dispute or difference for arbitration."

11. In Encon Builders (supra), this court proceeded on the assumption that the following clause was an arbitration agreement, as that issue was not disputed:

"In case of any dispute arising out of the agreement the matter shall be referred to the Managing Director, Bihar State Mineral Development Corporation Limited, Ranchi, whose decision shall be final and binding."

The clause specifically provided for `disputes being referred to the Managing Director' and made the said authority's decision not only final, but also binding on the parties. Therefore it can be said that it answers the tests of an arbitration agreement. The issue considered therein was whether 12 the High Court committed an error in refusing to refer the dispute to arbitration, even after finding the clause to be an arbitration agreement, by presuming bias in view of the fact that the named arbitrator was an employee of one of the parties to the dispute. This Court held that disputes were arbitrable in terms of the said clause. Be that as it may. A similar clause was to be arbitration agreement.


12. In Mallikarjun v. Gulbarga University - 2004 (1) SCC 372, this court held the following clause was a valid arbitration agreement :

"The decision of the Superintending Engineer of the Gulbarga Circle for the time being shall be final, conclusive, and binding on all parties to the contract upon all questions relating to the meaning of the specifications, designs, drawings and instructions herein before mentioned and as to the quality of workmanship or material used on the work, or as to any other question, claim, right, matter, or thing whatsoever, in any way arising out of, or relating to the contract, designs, drawings, specifications, estimates, instructions, orders or those conditions, or otherwise concerning the works of the execution, or failure to execute the same, whether arising during the progress of the work, or after the completion or abandonment thereof in case of dispute arising between the contractor and. Gulbarga University."

This court after referring to the essentials of an arbitration agreement laid down in Encon Builders held that the above clause is an arbitration agreement as it answered the test of reference of dispute for decision and made the decision of the authority final and binding. This court held :

13 "Applying the aforesaid principle to the present case, Clause 30 requires that the Superintending Engineer, Gulbarga Circle, Gulbarga, to give his decision on any dispute that may arise out of the contract. Further we also find that the agreement postulates present or future differences in connection with some contemplated affairs inasmuch as also there was an agreement between the parties to settle such difference by a private tribunal, namely, the Superintending Engineer, Gulbarga Circle, Gulbarga. It was also agreed between the parties that they would be bound by the decision of the tribunal. The parties were also ad idem."

The clause for consideration in this case

13. Clause 10 of the Conditions of Contract which is the subject of controversy reads thus:

"Clause 10: The Engineer-in-Charge shall have power to make any alterations in or additions to the original specifications, drawings, designs and instructions that may appear to him necessary and advisable during the progress of work, and the contractor shall be bound to carry out the work in accordance with any instructions which may be given to him in writing signed by the Engineer-in-Charge and such alterations shall not invalidate the contract, and any additional work which the contractor may be directed to do in the manner above specified as part of the work shall be carried out by the contractor on the same conditions in all respects on which he agreed to do the main work, and at the same rates as are specified in the tender for the main work. The time for the completion of the work shall be extended in the proportion that the additional work bears to the original contract work and the certificate of the Engineer-in-Charge shall be conclusive as to such proportion. And if the additional work includes any class of work for which no rate is specified in this contract, then such class of work shall be carried out at the rates entered in the sanctioned schedule of rates of the locality during the period when the work is being carried on and if such last mentioned class of work is not entered in the schedule of rates of the district then the contractor shall within seven days of the date of the rate which it is his intention to charge for such class of work, and if the Engineer-in-Charge does not agree to this rate he shall be noticed in writing be at liberty to cancel his order to carry out such class of work and arrange to carry it out in such manner as he may consider advisable.

No deviations from the specifications stipulated in the contract nor additional items of work shall ordinarily be carried out by the contractor, 14 nor shall any altered, additional or substituted work be carried out by him, unless the rates of the substituted, altered or additional items have been approved and fixed in writing by the Engineer-in-Charge, the contractor shall be bound to submit his claim for any additional work done during any month on or before the 15th days of the following month accompanied by a copy of the order in writing of the Engineer-in-Charge for the additional work and that the contractor shall not be entitled of any payment in respect of such additional work if he fails to submit his claim within the aforesaid period. Provided always that if the contractor shall commence work or incur any expenditure in respect thereof before the rates shall have been determined as lastly hereinbefore mentioned, in such case he shall only be entitled to be paid in respect of the work carried out or expenditure incurred by him prior to the date of the determination of the rates as aforesaid according to such rate or rates as shall be fixed by the Engineer-in-Charge. In the event of a dispute, the decision of the Superintending Engineer of the Circle will be final."

(emphasis supplied)

14. A reading of the said clause shows that it is a clause relating to power of the Engineer-in-Chief to make additions and alterations in the drawings and specifications and execution of non-tendered additional items of work (that is items of work which are not found in the bill of quantities or schedule of work). It provides for the following: a) that the Engineer-in-charge could make additions and alterations in the drawings/specifications; and that such alterations and additions will not invalidate the contract, but will entitle the contractor to extension of time for completion of work proportionately; b) that if the additional work be executed is an item for which the rate is not specified in the contract (or in the schedule of rates for the district), the contractor shall specify the rate and the Engineer-in- 15 charge may either accept the rate or cancel the order to execute that particular work; c) that if the contractor commences the work with reference to an item for which there is no rate in the contract and there is no agreement in regard to the rate for execution of such work, he shall be paid at the rates fixed by the Engineer-in -Charge; and d) that if the contractor disputes the rate fixed by the Engineer-in- Charge, the decision of the Superintending Engineer in regard to rate for such non-scheduled item shall be final.

15. We may next examine whether the last sentence of the proviso to clause 10 could be considered to be an arbitration agreement. It does not refer to arbitration as the mode of settlement of disputes. It does not provide for reference of disputes between the parties to arbitration. It does not make the decision of the Superintending Engineer binding on either party. It does not provide or refer to any procedure which would show that the Superintending Engineer is to act judicially after considering the submissions of both parties. It does not disclose any intention to make the Superintending Engineer an arbitrator in respect of disputes that may arise between the Engineer-in-Charge and the contractor. It does not make the decision of the Superintending Engineer final on any dispute, other than the 16 claim for increase in rates for non-tendered items. It operates in a limited sphere, that is, where in regard to a non-tendered additional work executed by the contractor, if the contractor is not satisfied with the unilateral determination of the rate therefor by the Engineer-in-Charge the rate for such work will be finally determined by the Superintending Engineer. It is a provision made with the intention to avoid future disputes regarding rates for non-tendered item. It is not a provision for reference of future disputes or settlement of future disputes. The decision of superintending Engineer is not a judicial determination, but decision of one party which is open to challenge by the other party in a court of law. The said clause can by no stretch of imagination be considered to be an arbitration agreement. The said clause is not, and was never intended to be, a provision relating to settlement of disputes.


16. That clause 10 was never intended to be an arbitration agreement is evident from the contract itself. It is relevant to note the Standard Conditions of Contract of the state government, as originally formulated consisted a provision (Clause 23) relating to settlement of disputes by arbitration, which is extracted below :

"Except where otherwise provided in the contract, all questions and disputes relating to the meaning of the specifications, designs, drawings 17 and instructions herein before mentioned and as to the quality of workmanship, or materials used on the work, or as to any other question, claim, right, matter or thing whatsoever, in any way arising out of or relating to the contract, designs, drawing, specifications, estimates, instructions, orders or these conditions, or otherwise concerning the work, or the execution, or failure to execute the same, whether arising during the progress of the work or after the completion or abandonment thereof shall be referred to the sole arbitration of a Superintending Engineer of the State Public Works Department unconnected with the work at any stage nominated by the Chief Engineer concerned. If there be no such Superintending Engineer, it should be refereed to the sole arbitration of Chief Engineer concerned. It will be no objection to any such appointment that the arbitrator so appointed is a government servant. The award of the arbitrator so appointed shall be final, conclusive and binding on all parties to this Contract."

The said clause was deleted by the State Government from the Standard Conditions of Contract by official Memorandum dated 24.12.1981. Contracts entered by the State Government thereafter did not have the said arbitration clause, though the other Conditions of Contract remained the same. The contracts in all these cases are of a period subsequent to 24.12.1981 and the Conditions of Contract forming part of these contracts do not contain the arbitration clause. When the State Government has consciously and intentionally deleted the provision for arbitration from its contracts, it will be a travesty of justice to read another clause in the contract providing for execution of non-tendered items and the method of determination of the rates therefor, as a provision for arbitration. 18

17. In fact, in Executive Engineer RCO vs. Suresh Chandra Panda [1999 (9) SCC 92], this Court considered the effect of the said clause relating to execution of non-tendered items, vis-`-vis clause 23 in a pre-1981 contract. This court held that the said clause (then numbered as clause 11, numbered as clause 10 in subsequent contracts) was a provision which excluded the issue relating to finality of rates, from the scope of arbitration agreement contained in clause 23 on the following reasoning : "Under Clause 11 of the contract, there is an elaborate provision dealing with the power of the Engineer-in Charge to make any alterations or additions to the original specifications, drawings, designs and instructions. It, inter alia, provides that if for such alterations or additions no rate is specified in the contract, then the rates which are entered in the sanctioned schedule of rates of the locality during the period when the work is being carried out, would be paid. However, if this class of work, not provided for in the sanctioned schedule of rates then the contractor has the right, in the manner specified in that clause, to inform the Engineer-in-Charge of the rate at which he intends to carry out that work. If the Engineer-in- Charge does not agree to this rate he is given the liberty to cancel his order and arrange to carry out such class of work in such manner as he may consider advisable. The clause further provides that if the contractor commences such additional work or incurs any expenditure in respect of it before the rate are determined as specified in that clause, then the rate or rates shall be as fixed by the Engineer-in-Charge. In the event of a dispute, the decision of the Superintendent Engineer of the circle will be final. Under Clause 23, except as otherwise provided in the contract, all disputes are arbitrable as set out in that clause. The finality of rates, therefore, under Clause 11 is a provision to the contrary in the contract which is excluded from Clause 23."

Thus, even when the Standard Conditions of Contract contained a provision for arbitration (vide clause 23), clause 10 was considered to be a provision dealing with a matter excepted from arbitration. Be that as it may. The proviso to clause 10, which provides that the decision of the Superintending 19 Engineer is `final', merely discloses an intention to exclude the rates for extra items decided by the Superintending Engineer from the scope of arbitration, as an excepted matter, when there was an arbitration agreement (clause 23) in the contract. When the arbitration agreement was deleted, provision dealing with non-tendered items can not be described as an arbitration agreement. Be that as it may.


18. We therefore allow these appeals, set aside the orders of the High Court appointing the arbitrator and dismiss the applications for appointment of arbitrator.

..................................J.

(R V Raveendran) New Delhi;


STATE OF GOA v. M/S PRAVEEN ENTERPRISES [2011] INSC 563 (4 July 2011)

Judgement
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 4987 OF 2011 [Arising out of SLP [C] No.15337 of 2009]

State of Goa ... Appellant
V/s.
Praveen Enterprises ... Respondent

R.V.RAVEENDRAN, J.

Leave granted.


2. Under an agreement dated 4.11.1992, the appellant (State of Goa) entrusted a construction work (Farm Development Works in Command Area of Water Course No.3 and 3A of minor M-3 of SIP in Salcette Taluka) to the respondent. Clause 25 of the agreement provided for settlement of disputes by arbitration, relevant portions of which are extracted below: "Except where otherwise provided in the contract, all questions and disputes relating to the meaning of the specifications, designs, drawings and instructions herein before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim right matter or thing whatsoever, in any way arising out of or relating to the contract, designs, drawings, specifications, estimates, 2 instructions orders or these conditions or otherwise concerning the works, or the execution or failure to execute the same whether arising during the progress of the work or after the completion or abandonment thereof shall be referred to the sole arbitration of the person appointed by the Chief Engineer, Central Public Works Department in charge of the work at the time of dispute...................It is a term of contract that the party invoking arbitrations shall specify the dispute or disputes to be referred to arbitration under this clause together with the amount or amounts claimed in respect of each such disputes."

As per the contract, the work had to be commenced on 16.11.1992 and completed by 5.5.1994. On the ground that the contractor did not complete the work even by the extended date of completion (31.3.1995), the contract was terminated by the appellant.

3. Respondent raised certain claims and gave a notice to the appellant to appoint an arbitrator in terms of the arbitration clause. As the appellant did not do so, the respondent filed an application under section 11 of the Arbitration and Conciliation Act, 1996 (`Act' of `new Act' for short) for appointment of an arbitrator. By order dated 4.12.1998 the said application was allowed and Mr. S.V.Salilkar, retired Adviser, Konkan Railway Corporation was appointed as the sole arbitrator. The arbitrator entered upon the reference on 22.2.1999 and called upon the parties to file their statement.

4. The respondent filed its claim statement before the arbitrator on 15.4.1999. The appellant filed its Reply Statement with counter claim on 3 30.6.1999. The arbitrator considered the fourteen claims of the contractor and four counter claims of the appellant. The Arbitrator made an award dated 10.7.2000. He awarded to the respondent, Rs.1,00,000/- towards claim No.2 with interest at 12% per annum from 26.8.1998 to 19.2.1999; Rs.3,63,416/- towards claim No.3 with interest at 12% per annum from 18.9.1995 to 22.2.1999; and Rs.59,075/- towards claim No. 14 (additional claim No. ii) with interest at 12% per annum from 18.9.1995 to 22.2.1999. In regard to the counter claims made by the appellant, the arbitrator awarded to the appellant Rs.2,94,298/- without any interest in regard to counter claim No.3. The arbitrator rejected the other claims of respondent and appellant. He awarded simple interest at 18% per annum on the award amount from the expiry of one month from the date of the award and directed both parties to bear their respective costs.


5. Feeling aggrieved the respondent filed an application under section 34 of the Act, challenging the award insofar as (i) rejection of its other claims; and (ii) award made on counter claim No.3. The civil court (Adhoc Additional District Judge, Fast Track Court No.1, South Goa) disposed of the matter upholding the award in regard to the claims of the respondent but accepted the objection raised by the respondent in regard to award made on the counter claim. The court held that the arbitrator could not enlarge the 4 scope of the reference and entertain either fresh claims by the claimants or counter claims from the respondent.

6. The appellant challenged the said judgment by filing an arbitration appeal before the High Court. The High Court of Bombay dismissed the appeal by judgment dated 31.8.2007. The High Court held that the counter claims were bad in law as they were never placed before the court by the appellant (in the proceedings under section 11 of the Act for appointment of arbitrator) and they were not referred by the court to arbitration. The High Court held that in such circumstances arbitrator had no jurisdiction to entertain a counter claim. The High Court followed its earlier decision in Charuvil Koshy Verghese v. State of Goa - 1998 (2) SCC 21. In that case, an application was made by a contractor under Section 20 of the Arbitration Act, 1940 (`old Act' for short), for filing the arbitration agreement and referring the disputes to the arbitrator. In its reply statement to the said application, the respondent did not assert its counter claim. The court allowed the application under section 20 and appointed an arbitrator to decide the disputes raised by the contractor. However when the matter went before the arbitrator, the respondent therein made a counter claim, which was allowed by the arbitrator. The Bombay High Court held that the 5 arbitrator had no jurisdiction to entertain or allow such a counter claim as the same had neither been placed before the court in the proceedings under section 20 nor the court had referred it to the arbitrator. The said judgment of the High Court is challenged in this appeal by special leave.

7. The appellant contends as a respondent in arbitration proceedings, in the absence of a bar in the arbitration agreement, it was entitled to raise its counter claims before the arbitrator, even though it had not raised them in its statement of objections to the proceedings under section 11 of the Act. It further contends that section 11 of the Act does not contemplate `reference of disputes' by the Chief Justice or his designate; and the High Court committed a serious error in holding that in the absence of a reference by the court, the arbitrator had no jurisdiction to entertain a counter claim, by following its earlier decision in Charuvil Koshy Verghese (supra), rendered with reference to section 20 of the old Act, which is materially different from section 11 of the new Act. The respondent supported the decision of the High Court, contending that having regard to the provisions of section 21 of the Act, an arbitrator will have jurisdiction to decide only those disputes which were raised and referred to him by the court.

6

8. Therefore the question that arises for our consideration is as under: Whether the respondent in an arbitration proceedings is precluded from making a counter-claim, unless a) it had served a notice upon the claimant requesting that the disputes relating to that counter-claim be referred to arbitration and the claimant had concurred in referring the counter claim to the same arbitrator; and/or b) it had set out the said counter claim in its reply statement to the application under section 11 of the Act and the Chief Justice or his designate refers such counter claim also to arbitration. What is `Reference to arbitration'

9. `Reference to arbitration' describes various acts. Reference to arbitration can be by parties themselves or by an appointing authority named in the arbitration agreement or by a court on an application by a party to the arbitration agreement. We may elaborate. (a) If an arbitration agreement provides that all disputes between the parties relating to the contract (some agreements may refer to some exceptions) shall be referred to arbitration and that the decision of the arbitrator shall be final and binding, the `reference' contemplated is the act of parties to the arbitration agreement, referring their disputes to an agreed arbitrator to settle the disputes.

7 (b) If an arbitration agreement provides that in the event of any dispute between the parties, an authority named therein shall nominate the arbitrator and refer the disputes which required to be settled by arbitration, the `reference' contemplated is an act of the appointing authority referring the disputes to the arbitrator appointed by him.

(c) Where the parties fail to concur in the appointment of arbitrator/s as required by the arbitration agreement, or the authority named in the arbitration agreement failing to nominate the arbitrator and refer the disputes raised to arbitration as required by the arbitration agreement, on an application by an aggrieved party, the court can appoint the arbitrator and on such appointment, the disputes between the parties stand referred to such arbitrator in terms of the arbitration agreement.

10. Reference to arbitration can be in respect of all disputes between the parties or all disputes regarding a contract or in respect of specific enumerated disputes. Where `all disputes' are referred, the arbitrator has the jurisdiction to decide all disputes raised in the pleadings (both claims and counter claims) subject to any limitations placed by the arbitration agreement. Where the arbitration agreement provides that all disputes shall be settled by arbitration but excludes certain matters from arbitration, then, the arbitrator will exclude the excepted matter and decide only those disputes which are arbitrable. But where the reference to the arbitrator is to 8 decide specific disputes enumerated by the parties/court/appointing authority, the arbitrator's jurisdiction is circumscribed by the specific reference and the arbitrator can decide only those specific disputes.


11. Though an arbitration agreement generally provides for settlement of future disputes by reference to arbitration, there can be `ad-hoc' arbitrations relating to existing disputes. In such cases, there is no prior arbitration agreement to refer future disputes to arbitration. After a dispute arises between the parties, they enter into an arbitration agreement to refer that specific dispute to arbitration. In such an arbitration, the arbitrator cannot enlarge the scope of arbitration by permitting either the claimant to modify or add to the claim or the respondent to make a counter claim. The arbitrator can only decide the dispute referred to him, unless the parties again agree to refer the additional disputes/counter claims to arbitration and authorize the arbitrator to decide them.


12. `Reference to arbitration' can be in respect of reference of disputes between the parties to arbitration, or may simply mean referring the parties to arbitration. Section 8 of the Act is an example of referring the parties to arbitration. While section 11 contemplates appointment of arbitrator [vide 9 sub-sections (4), (5) and (9)] or taking necessary measure as per the appointment procedure under the arbitration agreement [vide sub-section (6)], section 8 of the Act does not provide for appointment of an arbitrator, nor referring of any disputes to arbitration, but merely requires the judicial authority before whom an action is brought in a matter in regard to which there is an arbitration agreement, to refer the parties to arbitration. When the judicial authority finds that the subject matter of the suit is covered by a valid arbitration agreement between the parties to the suit, it will refer the parties to arbitration, by refusing to decide the action brought before it and leaving it to the parties to have recourse to their remedies by arbitration. When such an order is made, parties may either agree upon an arbitrator and refer their disputes to him, or failing agreement, file an application under section 11 of the Act for appointment of an arbitrator. The judicial authority `referring the parties to arbitration' under section 8 of the Act, has no power to appoint an arbitrator. It may however record the consent of parties to appoint an agreed arbitrator. Sections 21 and 43 of the Act

13. Section 21 provides that unless otherwise agreed by the parties, the arbitral proceedings in respect of a particular dispute commences on the date 10 on which a request for that dispute to be referred to arbitration is received by the respondent. Taking a cue from the said section, the respondent submitted that arbitral proceedings can commence only in regard to a dispute in respect of which notice has been served by a claimant upon the other party, requesting such dispute to be referred to arbitration; and therefore, a counter claim can be entertained by the arbitrator only if it has been referred to him, after a notice seeking arbitration in regard to such counter claim. On a careful consideration we find no basis for such a contention. The purpose of section 21 is to specify, in the absence of a provision in the arbitration agreement in that behalf, as to when an arbitral proceedings in regard to a dispute commences. This becomes relevant for the purpose of section 43 of the Act. Sub-section (1) of section 43 provides that the Limitation Act 1963 shall apply to arbitrations as it applies to proceedings in courts. Sub-section (2) of section 43 provides that for the purposes of section 43 and the Limitation Act, 1963, an arbitration shall be deemed to have commenced on the date referred to in section 21 of the Act. Having regard to section 43 of the Act, any claim made beyond the period of limitation prescribed by the Limitation Act, 1963 will be barred by limitation and the arbitral tribunal will have to reject such claims as barred by limitation. 11

14. Section 3 of the Limitation Act, 1963 provides for bar of limitation and is extracted below:

"3. Bar of Limitation. (1) Subject to the provisions contained in sections 4 to 24 (inclusive), every suit instituted, appeal preferred, and application made after the prescribed period shall be dismissed although limitation has not been set up as a defence.

(2) For the purposes of this Act,- (a) a suit is instituted,- (i) in an ordinary case, when the plaint is presented to the proper officer;

(ii) in the case of a pauper, when his application for leave to sue as a pauper is made; and (iii) in the case of a claim against a company which is being wound up by the court, when the claimant first sends in his claim to the official liquidator;

(b) any claim by way of a set off or a counter claim, shall be treated as a separate suit and shall be deemed to have been instituted- (i) in the case of a set off, on the same date as the suit in which the set off is pleaded; (ii) in the case of a counter claim, on the date on which the counter claim is made in court; (c) an application by notice of motion in a High Court is made when the application is presented to the proper officer of that court."

(emphasis supplied)

15. In regard to a claim which is sought to be enforced by filing a civil suit, the question whether the suit is within the period of limitation is decided with reference to the date of institution of the suit, that is, the date of 12 presentation of a plaint. As Limitation Act, 1963 is made applicable to arbitrations, there is a need to specify the date on which the arbitration is deemed to be instituted or commenced as that will decide whether the proceedings are barred by limitation or not. Section 3 of Limitation Act, 1963 specifies the date of institution for suit, but does not specify the date of `institution' for arbitration proceedings. Section 21 of the Act supplies the omission. But for section 21, there would be considerable confusion as to what would be the date of `institution' in regard to the arbitration proceedings. It will be possible for the respondent in an arbitration to argue that the limitation has to be calculated as on the date on which statement of claim was filed, or the date on which the arbitrator entered upon the reference, or the date on which the arbitrator was appointed by the court, or the date on which the application was filed under section 11 of the Act. In view of section 21 of the Act providing that the arbitration proceedings shall be deemed to commence on the date on which "the request for that dispute to be referred to arbitration is received by the respondent" the said confusion is cleared. Therefore the purpose of section 21 of the Act is to determine the date of commencement of the arbitration proceedings, relevant mainly for deciding whether the claims of the claimant are barred by limitation or not. 13

16. There can be claims by a claimant even without a notice seeking reference. Let us take an example where a notice is issued by a claimant raising disputes regarding claims `A' and `B' and seeking reference thereof to arbitration. On appointment of the arbitrator, the claimant files a claim statement in regard to the said claims `A' and `B'. Subsequently if the claimant amends the claim statement by adding claim `C' [which is permitted under section 23(3) of the Act] the additional claim `C' would not be preceded by a notice seeking arbitration. The date of amendment by which the claim `C' was introduced, will become the relevant date for determining the limitation in regard to the said claim `C', whereas the date on which the notice seeking arbitration was served on the other party, will be the relevant date for deciding the limitation in regard to Claims `A' and `B'. Be that as it may.


17. As far as counter claims are concerned, there is no room for ambiguity in regard to the relevant date for determining the limitation. Section 3(2)(b) of Limitation Act, 1963 provides that in regard to a counter claim in suits, the date on which the counter claim is made in court shall be deemed to be the date of institution of the counter claim. As Limitation Act, 1963 is made applicable to arbitrations, in the case of a counter claim by a respondent in 14 an arbitral proceedings, the date on which the counter claim is made before the arbitrator will be the date of "institution" in so far as counter claim is concerned. There is, therefore, no need to provide a date of `commencement' as in the case of claims of a claimant. Section 21 of the Act is therefore not relevant for counter claims. There is however one exception. Where the respondent against whom a claim is made, had also made a claim against the claimant and sought arbitration by serving a notice to the claimant but subsequently raises that claim as a counter claim in the arbitration proceedings initiated by the claimant, instead of filing a separate application under section 11 of the Act, the limitation for such counter claim should be computed, as on the date of service of notice of such claim on the claimant and not on the date of filing of the counter claim. Scope of sections 11 and 23 of the Act

18. Section 11 refers to appointment of arbitrators. Sub-sections (4), (5), (6) and (9) of section 11 relevant for our purpose are extracted below: "(4) If the appointment procedure in sub-section (3) applies and- (a) a party fails to appoint an arbitrator within thirty days from the receipt of a request to do so from the other party; or (b) the two appointed arbitrators fail to agree on the third arbitrator within thirty days from the date of their appointment, 15 the appointment shall be made, upon request of a party, by the Chief Justice or any person or institution Designated by him.

(5) Failing any agreement referred to in sub-section (2), in an arbitration with a sole arbitrator, if the parties fail to agree on the arbitrator within thirty days from receipt of a request by one party from the other party to so agree the appointment shall be made, upon request of a party, by the Chief Justice or any person or institution Designated by him.

(6) Where, under an appointment procedure agreed upon by the parties,- (a) a party fails to act as required under that procedure; or (b) the parties, or the two appointed arbitrators, fail to reach an agreement expected of them under that procedure; or (c) a person, including an institution, fails to perform any function entrusted to him or it under that procedure, a party may request the Chief Justice or any person or institution Designated by him to take the necessary measure, unless the agreement on the appointment procedure provides other means for securing the appointment.

xxx xxx xxx (9) In the case of appointment of sole or third arbitrator in an international commercial arbitration, the Chief Justice of India or the person or institution designated by him may appoint an arbitrator of a nationality other than the nationalities of the parties where the parties belong to different nationalities."

(emphasis supplied)

19. Section 23 relating to filing of statements of claim and defence reads thus: "23. Statements of claim and defence.- (1) Within the period of time agreed upon by the parties or determined by the arbitral tribunal, the claimant shall state the facts supporting his claim, the points at issue and the relief or remedy sought, and the respondent shall state his defence in 16 respect of these particulars, unless the parties have otherwise agreed as to the required elements of those statements.

(2) The parties may submit with their statements all documents they consider to be relevant or may add a reference to the documents or other evidence they will submit.

(3) Unless otherwise agreed by the parties, either party may amend or supplement his claim or defence during the course of the arbitral proceedings, unless the arbitral tribunal considers it inappropriate to allow the amendment or supplement having regard to the delay in making it."

(emphasis supplied) Section 2 contains the definitions. Sub-section (9) clarifies that except in sections 25(a) and 32(2)(a) , any reference in the Act to a `claim' will apply to a `counter-claim'. The said sub-section reads thus: "(9) Where this Part, other than clause (a) of section 25 or clause (a) of sub-section (2) of section 32, refers to a claim, it shall also apply to a counterclaim, and where it refers to a defence, it shall also apply to a defence to that counterclaim."


20. In contrast, section 20 of the old Act which provided for applications to file the arbitration agreement in court, read as under:

"20. Application to file in Court arbitration agreement. (1) Where any persons have entered into an arbitration agreement before the institution of any suit with respect to the subject matter of the agreement or any part of it, and where a difference has arisen to which the agreement applies, they or any of them, instead of proceeding under Chapter II, may apply to a Court having jurisdiction in the matter to which the agreement relates, that the agreement be filed in Court.

(2) The application shall be in writing and shall be numbered and registered as a suit between one or more of the parties interested or claiming to be interested as plaintiff or plaintiffs and the remainder as defendant or defendants, if the application has been presented by all the 17 parties, or, if otherwise, between the applicant as plaintiff and the other parties as defendants.

(3) On such application being made, the Court shall direct notice thereof to be given to all parties to the agreement other than the applicants, requiring them to show cause within the time specified in the notice why the agreement should not be filed.

(4) Where no sufficient cause is shown, the Court shall order the agreement to be filed, and shall make an order of reference to the arbitrator appointed by the parties, whether in the agreement or otherwise, or, where the parties cannot agree upon an arbitrator, to an arbitrator appointed by the Court.

(5) Thereafter the arbitration shall proceed in accordance with, and shall be governed by, the other provisions of this Act so far as they can be made applicable."

(emphasis supplied)

21. Section 20 of the old Act required the court while ordering the arbitration agreement to be filed, to make an order of reference to the arbitrator. The scheme of the new Act requires minimal judicial intervention. Section 11 of the new Act, on the other hand, contemplates the Chief Justice or his designate appointing the arbitrator but does not contain any provision for the court to refer the disputes to the arbitrator. Sub-sections (4), (5) and (9) of section 11 of the Act require the Chief Justice or his designate to appoint the arbitrator/s. Sub-section (6) requires the Chief Justice or his designate to `take the necessary measure' when an application is filed by a party complaining that the other party has failed to act as required under the appointment procedure. All these sub-sections contemplate an applicant 18 filing the application under section 11, only after he has raised the disputes and only when the respondent fails to co-operate/concur in regard to appointment of arbitrator.

22. Section 23 of the Act makes it clear that when the arbitrator is appointed, the claimant is required to file the statement and the respondent has to file his defence statement before the Arbitrator. The claimant is not bound to restrict his statement of claim to the claims already raised by him by notice, "unless the parties have otherwise agreed as to the required elements" of such claim statement. It is also made clear that "unless otherwise agreed by the parties" the claimant can also subsequently amend or supplement the claims in the claim statement. That is, unless the arbitration agreement requires the Arbitrator to decide only the specifically referred disputes, the claimant can while filing the statement of claim or thereafter, amend or add to the claims already made. Similarly section 23 read with section 2(9) makes it clear that a respondent is entitled to raise a counter claim "unless the parties have otherwise agreed" and also add to or amend the counter claim, "unless otherwise agreed". In short, unless the arbitration agreement requires the Arbitrator to decide only the specifically referred disputes, the respondent can file counter claims and amend or add to 19 the same, except where the arbitration agreement restricts the arbitration to only those disputes which are specifically referred to arbitration, both the claimant and respondent are entitled to make any claims or counter claims and further entitled to add to or amend such claims and counter claims provided they are arbitrable and within limitation.


23. Section 11 of the Act requires the Chief Justice or his designate only to appoint the arbitrator/s. It does not require the Chief Justice or his designate to identify the disputes or refer them to the Arbitral Tribunal for adjudication. Where the appointment procedure in an arbitration agreement requires disputes to be formulated and specifically referred to the arbitrator and confers jurisdiction upon the arbitrator to decide only such referred disputes, when an application is filed under section 11(6) of the Act, alleging that such procedure is not followed, the Chief Justice or his designate will take necessary measures under section 11(6) of the Act to ensure compliance by the parties with such procedure. Where the arbitration agreement requires the disputes to be formulated and referred to arbitration by an appointing authority, and the appointing authority fails to do so, the Chief Justice or his designate will direct the appointing authority to formulate the disputes for reference as required by the arbitration agreement. The assumption by the 20 courts below that a reference of specific disputes to the Arbitrator by the Chief Justice or his designate is necessary while making appointment of arbitrator under section 11 of the Act, is without any basis. Equally baseless is the assumption that where one party filed an application under section 11 and gets an arbitrator appointed the arbitrator can decide only the disputes raised by the applicant under section 11 of the Act and not the counter claims of the respondent.

24. Section 23 of the Act enables the claimant to file a statement of claim stating the facts supporting his claim, the points at issue and the relief or remedy sought by him and enables the respondent to state his defence in respect of those claims. Section 2(9) provides that if any provision [other than section 25 (a) or section 32(2)(a)], refers to a "claim", it shall apply to a "counter claim" and where it refers to a "defence", it shall also apply to a defence to that counter claim. This would mean that a respondent can file a counter claim giving the facts supporting the counter claim, the points at issue and the relief or remedy sought in that behalf and the claimant (who is the respondent in the counter claim) will be entitled to file his defence to such counter claim. Once the claims and counter claims are before the arbitrator, the arbitrator will decide whether they fall within the scope of the 21 arbitration agreement and whether he has jurisdiction to adjudicate on those disputes (whether they are claims or the counter claims) and if the answer is in the affirmative, proceed to adjudicate upon the same.

25. It is of some relevance to note that even where the arbitration proceedings were initiated in pursuance of a reference under section 20 of the old Act, this Court held (in Indian Oil Corporation Ltd. vs. Amritsar Gas Service and Ors. - 1991(1) SCC 533) that the respondent was entitled to raise counter claims directly before the arbitrator, where all disputes between parties are referred to arbitration. This Court observed : "The appellant's grievance regarding non-consideration of its counter- claim for the reason given in the award does appear to have some merit. In view of the fact that reference to arbitrator was made by this Court in an appeal arising out of refusal to stay the suit under Section 34 of the Arbitration Act and their reference was made of all disputes between the parties in the suit, the occasion to make a counter-claim in the written statement could arise only after the order of reference. The pleadings of the parties were filed before the arbitrator, and the reference covered all disputes between the parties in the suit. Accordingly, the counter-claim could not be made at any earlier stage. Refusal to consider the counter- claim for the only reason given in the award does, therefore, disclose an error of law apparent on the face of the award."

(emphasis supplied)

26. A counter claim by a respondent pre-supposes the pendency of proceedings relating to the disputes raised by the claimant. The respondent could no doubt raise a dispute (in respect of the subject matter of the counter 22 claim) by issuing a notice seeking reference to arbitration and follow it by an application under section 11 of the Act for appointment of Arbitrator, instead of raising a counter claim in the pending arbitration proceedings. The object of providing for counter claims is to avoid multiplicity of proceedings and to avoid divergent findings. The position of a respondent in an arbitration proceedings being similar to that of a defendant in a suit, he has the choice of raising the dispute by issuing a notice to the claimant calling upon him to agree for reference of his dispute to arbitration and then resort to an independent arbitration proceedings or raise the dispute by way of a counter claim, in the pending arbitration proceedings. Respondent's contentions

27. The respondent submitted that this Court in SBP & Co. vs. Patel Engineering Ltd. -- 2005 (8) SCC 618 and National Insurance Co.Ltd. v Boghara Polyfab Private Ltd. -- 2009 (1) SCC 267, has observed that while deciding an application under section 11 of the Act, the Chief Justice or his designate can decide the question whether the claim was a dead one (long time barred) that was sought to be resurrected. According to appellant the logical inference from this observation is that an application under section 11 should sufficiently enumerate and describe the claims to demonstrate that 23 they are within limitation. Extending the same logic, respondent contends that any counter claim by the respondent should also be described in his statement of objections with relevant particulars so that the Chief Justice or his designate could consider and pronounce whether such counter claim is barred by limitation. The respondent therefore argues that every claim unless specifically mentioned in the application under section 11 of the Act, and every counter claim unless specifically mentioned in the statement of objections, cannot be the subject matter of arbitration.

28. The aforesaid contention of the respondent is based on the erroneous premises that whenever an application is filed under section 11 of the Act, it is necessary for the Chief Justice or his Designate to consider and decide whether the claims or counter claims are barred by limitation or not. In SBP & Co. and Boghara Polyfab, this Court classified the questions that may be raised in an application under section 11 of the Act into three groups : (i) those which the Chief Justice/his designate shall have to decide; (ii) those which the Chief Justice/his designate may choose to decide or alternatively leave to the decision of the Arbitral Tribunal; and (iii) those which the Chief Justice/his designate should leave exclusively for the decision of the Arbitral Tribunal. This Court held that the issue whether a claim is dead claim (long 24 barred claim) is an issue which the Chief Justice or his designate may choose to decide or leave for the decision of the Arbitral Tribunal. The difference between a dead/stale claim and a mere time barred claim was explained by this Court in Indian Oil Corporation Ltd. v. M/s SPS Engineering Ltd. [1985] INSC 163; [2011 (2) SCALE 291 ] thus : - "When it is said that the Chief Justice or his designate may choose to decide whether the claim is a dead claim, it is implied that he will do so only when the claim is evidently and patently a long time barred claim and there is no need for any detailed consideration of evidence. We may elucidate by an illustration: If the contractor makes a claim a decade or so after completion of the work without referring to any acknowledgement of a liability or other factors that kept the claim alive in law, and the claim is patently long time barred, the Chief Justice or his designate will examine whether the claim is a dead claim (that is, a long time barred claim). On the other hand, if the contractor makes a claim for payment, beyond three years of completing of the work but say within five years of completion of work, and alleges that the final bill was drawn up and payments were made within three years before the claim, the court will not enter into a disputed question whether the claim was barred by limitation or not. The court will leave the matter to the decision of the Tribunal. If the distinction between apparent and obvious dead claims, and claims involving disputed issues of limitation is not kept in view, the Chief Justice or his designate will end up deciding the question of limitation in all applications under Section 11 of the Act."


29. The issue of limitation is not an issue that has to be decided in an application under section 11 of the Act. SBP & Co. and Boghara Polyfab held that the Chief Justice or his designate will not examine issues relating to limitation, but may consider in appropriate cases, whether the application was in regard to a claim which on the face of it was so hopelessly barred by 25 time, that it is already a dead/stale claim which did not deserve to be resurrected and referred to arbitration. The said decisions do not support the respondent's contention that the details of all claims should be set out in the application under section 11 of the Act and that details of all counter claims should be set out in the statement of objections, and that a claim or a counter claim which is not referred to or set out in the pleadings in the proceedings under section 11 of the Act, cannot be entertained or decided by the arbitral tribunal.


30. Reliance was next placed on the following passage from the Law and Practice of Commercial Arbitration in England [Mustill & Boyd - (1989) Second Edn. Page 131] to contend that the counter claim ought to have been submitted to the Arbitrator when he is appointed:

"The fourth situation, in which both the claim and the cross-claim are arbitrable, is the one most commonly encountered in practice. The arbitrator should carefully consider whether the subject matter of the counter claim was one of the matters submitted to him at the time of the appointment. If it is, then it is up to him whether to allow the matter to be raised by counter claim or made the subject of a separate arbitration. In practice, we have never known the second course to be followed. If, on the other hand, the cross-claim was not a dispute which was submitted to him, he should not entertain it unless it raises a pure defence, or unless the parties clearly agree that he is to have jurisdiction over it."

(emphasis supplied) 26 The said observations were made with reference to the Arbitration Law prevailing in United Kingdom in the year 1989, prior to the enactment of (English) Arbitration Act, 1996. Further the observations obviously related to an arbitration where specific disputes were referred to arbitration and consequently the arbitrator was bound to restrict himself to the disputes referred. We have already adverted to this aspect earlier.

31. The respondent lastly contended that the Court is required to ascertain the precise nature of the dispute which has arisen and then decide whether the dispute is one which falls within the terms of the arbitration clause, before appointing an arbitrator; and that could be done only if the claims are set out in the application under section 11 of the Act and the counter claims are set out in the statement of objections and court had an opportunity to examine it. It is therefore submitted that a dispute (relating to a claim or counter claim) not referred in the pleadings, is not arbitrable. Reliance was placed upon certain observations in the decision of the House of Lords in Heyman v. Darwins Ltd.-- 1942 AC 356. We extract below the paragraph containing the relied upon observations : "The law permits the parties to a contract to include in it as one of its terms an agreement to refer to arbitration disputes which may arise in connection with it, and the court of England enforce such a reference by staying legal proceedings in respect of any matter agreed to be referred "if 27 satisfied that there is no sufficient reason why the matter should not be referred in accordance with the submission." Arbitration Act, 1889, sec. 4. Where proceedings at law are instituted by one of the parties to a contract containing an arbitration clause and the other party, founding on the clause, applies for a stay, the first thing to be ascertained is the precise nature of the dispute which has arisen The next question is whether the dispute is one which falls within the terms of the arbitration clause. Then sometimes the question is raised whether the arbitration clause is still effective or whether something has happened to render it no longer operative. Finally, the nature of the dispute being ascertained, it having been held to fall within the terms of the arbitration clause, and the clause having been found to be still effective, there remains for the court the question whether there is any sufficient reason why the matter in dispute should not be referred to arbitration."

(emphasis supplied) The said observations were made while examining whether a suit should be stayed at the instance of the defendant on the ground that there was an arbitration agreement between the parties. If a party to an arbitration agreement files a civil suit and the defendant contends that the suit should be stayed and the parties should be referred to arbitration, necessarily, the court will have to find out what exactly is the subject matter of the suit, whether it would fall within the scope of the arbitration clause, whether the arbitration clause was valid and effective and lastly whether there was sufficient reason as to why the subject matter of the suit should not be referred to arbitration. The observations made in Heymen, in the context of an application seeking stay of further proceedings in a suit, are not relevant in respect of an application under section 11 of the Act. This Court has repeatedly held that the questions for consideration in an application under section 8 by a civil 28 court in a suit are different from the questions for consideration under section 11 of the Act. The said decision is therefore of no assistance. Summation

32. The position emerging from above discussion may be summed up as follows:

(a) Section 11 of the Act requires the Chief Justice or his designate to either appoint the arbitrator/s or take necessary measures in accordance with the appointment procedure contained in the arbitration agreement. The Chief Justice or the designate is not required to draw up the list of disputes and refer them to arbitration. The appointment of Arbitral Tribunal is an implied reference in terms of the arbitration agreement.

(b) Where the arbitration agreement provides for referring all disputes between the parties (whether without any exceptions or subject to exceptions), the arbitrator will have jurisdiction to entertain any counter claim, even though it was not raised at a stage earlier to the stage of pleadings before the Arbitrator. (c) Where however the arbitration agreement requires specific disputes to be referred to arbitration and provides that the arbitrator will have the jurisdiction to decide only the disputes so referred, the arbitrator's jurisdiction is controlled by the specific reference and he cannot travel 29 beyond the reference, nor entertain any additional claims or counter claims which are not part of the disputes specifically referred to arbitration. The position in this case

33. The arbitration clause in this case contemplates all disputes being referred to arbitration by a sole arbitrator. It refers to an Appointing Authority (Chief Engineer, CPWD), whose role is only to appoint the arbitrator. Though the arbitration clause requires the party invoking the arbitration to specify the dispute/s to be referred to arbitration, it does not require the appointing authority to specify the disputes or refer any specific disputes to arbitration nor requires the Arbitrator to decide only the referred disputes. It does not bar the arbitrator deciding any counter claims. In the absence of agreement to the contrary, it has to be held that the counter claims by the appellant were maintainable and arbitrable having regard to section 23 read with section 2(9) of the Act.


34. Counter claim no.(3) in regard to which Rs.2,94,298/- has been awarded by the Arbitrator relates to the cost of pipes entrusted by the appellant for carriage from store to site, which were not accounted for by the respondent. It is not shown to be barred by limitation. We find no error in 30 the reasoning of the arbitrator in awarding Rs.2,94,298/- under counter claim no.(3). Conclusion

35. In view of the above, this appeal is allowed and the order of the High Court affirming the judgment of the trial court in regard to counter claim No.3, is set aside. Consequently the award of arbitrator is upheld in its entirety and the challenge thereto by the respondent is rejected.
................................J.

(R V Raveendran) New Delhi;