REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOs. OF 2010
(Arising out of SLP (C) Nos.25043-25045 of 2008)
Kalabharati Advertising ...Appellant
Versus
Hemant Vimalnath Narichania
and Ors. ...Respondents
JUDGMENT
Dr. B.S. CHAUHAN, J.
1. Delay condoned. Leave granted.
2. These appeals have been preferred against the judgment and orders
dated 4.2.2008/13.2.2008 passed by the High Court of Judicature at Bombay
in Writ Petition No.2366 of 2007 and the consequential order dated
8.2.2008, as amended vide order dated 11.2.2008 passed by the Municipal
Corporation of Greater Mumbai by which the hoarding fixed by the
appellant in the Anand Darshan Co-operative Housing Society Ltd.,
Respondent No.13 (hereinafter called the "Society") had been removed in
spite of agreements between the parties.
3. Facts and circumstances giving rise to these appeals are that the
appellant who is carrying out a business of advertisement hoardings within
the city of Bombay approached the Society in 2001 for grant of permission
to erect a hoarding admeasuring 40'x20' in its compound. The Society
passed a Resolution in the year 2001, permitting the appellant to erect a
hoarding of the aforesaid measurement. The appellant applied to the
Municipal Corporation (hereinafter called the "Corporation") for grant of
necessary permission for erecting the same. The said application was
allowed by the Corporation vide order dated 4.8.2001. Subsequent thereto
an agreement dated 5.9.2001 was executed between the appellant and the
Society for a period of three years on various terms and conditions
mentioned therein, and was given effect to. The said agreement was
renewed after expiry of the period of three years in the year 2004 by the
Society and ultimately vide Resolution dated 12.8.2007 for a further period
of three years.
4. During this period, a Public Interest Litigation, being Writ Petition
No.1132 of 2002 was filed before the Bombay High Court by one Dr.
2
Anahita Peadoin against the Municipal Corporation of Greater Mumbai
pertaining to the grant of permission for hoardings in Mumbai alleging
various violations of guidelines issued by the Corporation for the said
purpose. The Bombay High Court while entertaining the writ petition
constituted a Committee to find out violations of the guidelines of the
hoardings in Mumbai and the Committee found that 266 hoardings including
that of the appellant had been in violation of the guidelines issued by the
Corporation. So far as the appellant is concerned, the Committee came to
the conclusion that the said hoarding had been in violation of condition
Nos.16(f) and 16(c), i.e., obstructing the air, light and ventilation and
situated in the compulsory open space.
5. The Bombay High Court vide its order dated 1.10.2002 directed the
aggrieved parties to file representation before the Statutory Authority, i.e.,
Deputy Municipal Commissioner, against the findings of the Committee
constituted by the Court. Accordingly, the appellant made a representation
before the said authority and the said representation was disposed of on
6.4.2004, after giving opportunity of hearing to the appellant and examining
the facts in the presence of officers/representatives of the respondent-
Corporation, coming to the conclusion that the hoarding of the appellant was
3
not violative of guideline No.16(f). So far as violation of guideline No.16(c)
was concerned, the appellant was directed to apply to the Chief Engineer
(DP) for condonation of compulsory open space clause of guidelines within
15 days with an observation that regularisation of the hoarding would be
subject to the outcome of Writ Petition No.1132 of 2002.
6. In pursuance to the order dated 6.4.2004, appellant approached the
said Authority vide representation dated 1.6.2004. The said representation
was marked/assigned to the Assistant Engineer (BP) and he was directed to
examine the case. The said Assistant Engineer (BP) City-III examined the
case and had also made physical verification of the hoarding and prepared
the report dated 16.7.2007 to the effect that there was no violation of clause
16(c) of the guidelines. The said report was placed before the Executive
Engineer (BP) City-I of the Corporation who approved the same vide order
dated 17.7.2007.
7. There had been some dispute between the Society and some of its
members and those members raised certain objections/complaints against the
erection of the hoarding in question. Those members approached the Co-
operative Court challenging the Resolution passed by the Society in favour
of the appellant for granting permission to erect the hoarding and also made
4
an application for interim relief. However, the Co-operative Court
dismissed the application for interim relief.
8. Being aggrieved, some of the members of the Society (Respondent
Nos.1 to 5) filed Writ Petition No.2366 of 2007 before the Bombay High
Court against the Society and the appellant for cancellation of the
permission granted in favour of the appellant. During the course of hearing
of the said writ petition on 4.2.2008, the Joint Municipal Commissioner
(Education), Shri S.S. Shinde filed an affidavit to withdraw the earlier order
approving the erection and for permission to pass a fresh order in accordance
with law. The court accepted the said affidavit and permitted the
Corporation to withdraw its earlier order with further liberty to pass fresh
orders without giving an opportunity of hearing to the appellant or the
Society as it had already been done while passing the earlier order. In
pursuance of the said order, a fresh order was passed by the respondent-
Corporation on 11.2.2008, not approving the erection of hoarding which had
earlier been approved. Hence, these appeals.
9. Shri Ravi Shankar Prasad, Ld. Senior Counsel for the appellant,
submitted that as the PIL, i.e., Writ Petition (Civil) No.1132 of 2002 in
5
which certain direction had been issued by the High Court and a Committee
was constituted to examine as to whether hoardings were in violation of the
guidelines and an action had been taken in pursuance thereof, is still
pending, even if the respondent nos.1 to 5 were aggrieved of any order of the
Corporation, they ought to have moved an application for intervention and
for further direction in the said Writ Petition No.1132 of 2002. An
independent writ petition could not have been filed. So far as the internal
dispute between the Society and some of its members is concerned, it is still
pending with the Co-operative Court. Only an application for interim relief
had been dismissed. Therefore, the writ petition itself was not maintainable
as the said respondents had chosen the forum of Co-operative Court under
the provisions of Maharashtra Co-operative Societies Act, 1960 (hereinafter
called as `Act"). The High Court had permitted the respondent-Corporation
to withdraw its earlier order and to pass a fresh order, that tantamounts to
conferring the jurisdiction of review upon the statutory authority, though
such power had not been conferred by the Statute. Therefore, the order
conferring such power itself is without jurisdiction. The Corporation passed
subsequent order without assigning any reason and giving opportunity of
hearing to the appellant. It is a clear cut case of legal malice. More so, the
respondent Nos. 1 to 5, have been permitted to withdraw the Writ Petition
6
No.2366 of 2007 itself vide order dated 13.2.2008, therefore, all orders
passed therein by the High Court as well as the consequential orders passed
by the Corporation stood automatically washed away. Thus, the appellant
should be permitted to continue its business with the Society as if no order
had ever been passed by the Court or Corporation in regard to the hoardings
in question.
10. On the contrary, Shri Atul Yeshwant Chitale, Ld. Senior Counsel
appearing for the respondent-Corporation, has submitted that a new policy
dated 10.1.2008 has come into existence. The case of the appellant shall be
considered strictly in accordance with the terms and conditions incorporated
therein. Thus, an opportunity should be given to the respondent-Corporation
to consider the case afresh.
Shri Ratan Kumar Singh, Ld. Counsel appearing for respondent nos.1
to 5 (original writ petitioners) has submitted that withdrawal of the writ
petition does not have any bearing on these appeals as the same had been
withdrawn after being satisfied that their grievances stood fully redressed by
the interim orders passed by the High Court and consequential orders passed
by the Corporation. The order passed by the Corporation could not be
challenged before this Court directly, without approaching the High Court.
7
The pendency of the dispute between the Society and its members before the
Co-operative Court could not create any hindrance for them to approach the
High Court by filing a fresh Writ Petition as they were not parties in the
earlier Writ Petition No.1132 of 2002. The hoardings in question had been
in violation of the guidelines of the Corporation and thus, subsequent orders
passed by the Corporation do not require any interference. Thus, the appeals
have no merit and are liable to be dismissed.
11. We have considered the rival submissions made by both the parties
and perused the record.
LEGAL ISSUES:
Review in absence of statutory provisions:
12. It is settled legal proposition that unless the statute/rules so permit,
the review application is not maintainable in case of judicial/quasi-judicial
orders. In absence of any provision in the Act granting an express power of
review, it is manifest that a review could not be made and the order in
review, if passed is ultra-vires, illegal and without jurisdiction. (vide: Patel
Chunibhai Dajibha v. Narayanrao Khanderao Jambekar & Anr., AIR
8
1965 SC 1457; and Harbhajan Singh v. Karam Singh & Ors., AIR 1966
SC 641).
13. In Patel Narshi Thakershi & Ors. v. Shri Pradyuman Singhji
Arjunsinghji, AIR 1970 SC 1273; Maj. Chandra Bhan Singh v. Latafat
Ullah Khan & Ors., AIR 1978 SC 1814; Dr. Smt. Kuntesh Gupta v.
Management of Hindu Kanya Mahavidhyalaya, Sitapur (U.P.) & Ors.,
AIR 1987 SC 2186; State of Orissa & Ors. v. Commissioner of Land
Records and Settlement, Cuttack & Ors., (1998) 7 SCC 162; and Sunita
Jain v. Pawan Kumar Jain & Ors., (2008) 2 SCC 705, this Court held
that the power to review is not an inherent power. It must be conferred
by law either expressly/specifically or by necessary implication and in
absence of any provision in the Act/Rules, review of an earlier order is
impermissible as review is a creation of statute. Jurisdiction of review can be
derived only from the statute and thus, any order of review in absence of any
statutory provision for the same is nullity being without jurisdiction.
14. Therefore, in view of the above, the law on the point can be
summarised to the effect that in absence of any statutory provision providing
for review, entertaining an application for review or under the garb of
clarification/ modification/correction is not permissible.
9
Case dismissed/withdrawn- effect on interim relief:
15. No litigant can derive any benefit from the mere pendency of a case in
a Court of Law, as the interim order always merges into the final order to be
passed in the case and if the case is ultimately dismissed, the interim order
stands nullified automatically. A party cannot be allowed to take any benefit
of his own wrongs by getting an interim order and thereafter blame the
Court. The fact that the case is found, ultimately, devoid of any merit, or the
party withdrew the writ petition, shows that a frivolous writ petition had
been filed. The maxim "Actus Curiae neminem gravabit", which means that
the act of the Court shall prejudice no-one, becomes applicable in such a
case. In such a situation the Court is under an obligation to undo the wrong
done to a party by the act of the Court. Thus, any undeserved or unfair
advantage gained by a party invoking the jurisdiction of the Court must be
neutralised, as the institution of litigation cannot be permitted to confer any
advantage on a party by the delayed action of the Court. (vide: Dr. A.R.
Sircar v. State of Uttar Pradesh & Ors., 1993 Supp. (2) SCC 734; Shiv
Shanker & Ors. v. Board of Directors, Uttar Pradesh State Road
Transport Corporation & Anr., 1995 Supp. (2) SCC 726; the Committee
of Management, Arya Inter College, Arya Nagar, Kanpur & Anr. v.
Sree Kumar Tiwary & Anr., AIR 1997 SC 3071; GTC Industries Ltd. v.
10
Union of India & Ors., AIR 1998 SC 1566; and Jaipur Municipal
Corporation v. C.L. Mishra, (2005) 8 SCC 423).
16. In Ram Krishna Verma & Ors. v. State of U.P. & Ors., AIR 1992
SC 1888, this Court examined the issue while placing reliance upon its
earlier judgment in Grindlays Bank Limited v. Income Tax Officer,
Calcutta & Ors., AIR 1980 SC 656 and held that no person can suffer from
the act of the Court and in case an interim order has been passed and the
petitioner takes advantage thereof, and ultimately the petition stands
dismissed, the interest of justice requires that any undeserved or unfair
advantage gained by a party invoking the jurisdiction of the Court must be
neutralized.
17. A similar view has been reiterated by this Court in Mahadeo
Savlaram Shelke & Ors. v. Pune Municipal Corporation & Anr., (1995)
3 SCC 33.
18. In South Eastern Coalfields Ltd. v. State of M.P. & Ors., AIR 2003
SC 4482, this Court examined this issue in detail and held that no one shall
suffer by an act of the Court. The factor attracting the applicability of
restitution is not the act of the Court being wrongful or a mistake or error
11
committed by the court; the test is whether an act of the party persuading the
Court to pass an order held at the end as not sustainable, has resulted in one
party gaining an advantage it would not have otherwise earned, or the other
party suffering an impoverishment which it would not have suffered but for
the order of the Court and the act of such party. There is nothing wrong in
the parties demanding to be placed in the same position in which they would
have been had the Court not intervened by its interim order, when at the end
of the proceedings, the Court pronounces its judicial verdict which does not
match with and countenance its own interim verdict. The injury, if any,
caused by the act of the Court shall be undone and the gain which the party
would have earned unless it was interdicted by the order of the Court would
be restored to or conferred on the party by suitably commanding the party
liable to do so. Any opinion to the contrary would lead to unjust if not
disastrous consequences. The Court further held :
".....Litigation may turn into a fruitful industry.
Though litigation is not gambling yet there is an element of
chance in every litigation. Unscrupulous litigants may feel
encouraged to approach the courts, persuading the Court to
pass interlocutory orders favourable to them by making out
a prima facie case when the issues are earlier to be heard
and determined on merits and if the concept of restitution is
excluded from application to interim orders, then the
litigant would stand to gain by swallowing the benefits
yielding out of the interim order even though the battle has
been lost at the end. This cannot be countenanced. We are,
therefore, of the opinion that the successful party finally
12
held entitled to a relief assessable in terms of money at the
end of the litigation, is entitled to be compensated......"
19. In Karnataka Rare Earth & Anr. v. Senior Geologist, Department
of Mines & Geology & Anr., (2004) 2 SCC 783, a similar view has been
reiterated by this Court observing that the party who succeeds ultimately is
to be placed in the same position in which they would have been if the Court
would not have protected them by issuing interim order.
20. The aforesaid judgments are passed on the application of legal maxim
"sublato fundamento cadit opus", which means in case a foundation is
removed, the superstructure falls.
21. In Badrinath v. State of Tamil Nadu & Ors., AIR 2000 SC 3243,
this Court observed that once the basis of a proceeding is gone, all
consequential acts, action, orders would fall to the ground automatically and
this principle of consequential order which is applicable to judicial and
quasi-judicial proceedings is equally applicable to administrative orders.
Court-cannot be used only for interim relief:
22. It is a settled legal proposition that the forum of the writ court
cannot be used for the purpose of giving interim relief as the only and the
13
final relief to any litigant. If the Court comes to the conclusion that the
matter requires adjudication by some other appropriate forum and relegates
the said party to that forum, it should not grant any interim relief in favour of
such a litigant for an interregnum period till the said party approaches the
alternative forum and obtains interim relief. (vide: State of Orissa v.
Madan Gopal Rungta, AIR 1952 SC 12; Amarsarjit Singh v. State of
Punjab, AIR 1962 SC 1305; State of Orissa v. Ram Chandra Dev, AIR
1964 SC 685; State of Bihar v. Rambalak Singh "Balak" & Ors., AIR
1966 SC 1441; and Premier Automobiles Ltd. v. Kamlakar Shantaram
Wadke & Ors., AIR 1975 SC 2238).
23. It is settled proposition that an order of withdrawal of a suit does not
amount to a decree of the court, which can be executed. (See:
Kandapazha Nadar & Ors. v. Chitraganiammal & Ors. AIR 2007
SC 1575).
24. It is not permissible for a party to file a writ petition, obtaining certain
orders during the pendency of the petition and withdraw the same
without getting proper adjudication of the issue involved therein and
insist that the benefits of the interim orders or consequential orders
14
passed in pursuance of the interim order passed by the writ court
would continue. The benefit of the
interim relief automatically gets withdrawn/neutralized on withdrawal of the
said petition. In such a case concept of restitution becomes applicable
otherwise the party would continue to get benefit of the interim order even
after loosing the case in the court. The court should also pass order
expressly neutralizing the effect of all consequential orders passed in
pursuance of the interim order passed by the court. Such express directions
may be necessary to check the rising trend among the litigants to secure the
relief as an interim measure and then avoid adjudication on merits. (Vide
Abhimanyoo Ram v. State of U.P., (2008) 17 SCC 73).
Legal Malice:
25. The State is under obligation to act fairly without ill will or malice- in
fact or in law. "Legal malice" or "malice in law" means something done
without lawful excuse. It is an act done wrongfully and wilfully without
reasonable or probable cause, and not necessarily an act done from ill feeling
and spite. It is a deliberate act in disregard to the rights of others. Where
malice is attributed to the State, it can never be a case of personal ill-will or
15
spite on the part of the State. It is an act which is taken with an oblique or
indirect object. It means exercise of statutory power for "purposes foreign to
those for which it is in law intended." It means conscious violation of the
law to the prejudice of another, a depraved inclination on the part of the
authority to disregard the rights of others, which intent is manifested by its
injurious acts. (Vide Addl. Distt. Magistrate, Jabalpur v. Shivakant
Shukla, AIR 1976 SC 1207; Smt. S.R. Venkataraman v. Union of India,
AIR 1979 SC 49; State of A.P. v. Goverdhanlal Pitti, AIR 2003 SC 1941;
Chairman and M.D., B.P.L. Ltd. V. S.P. Gururaja & Ors., (2003) 8 SCC
567; and West Bengal State Electricity Board v. Dilip Kumar Ray, AIR
2007 SC 976).
26. Passing an order for an unauthorized purpose constitutes malice in
law. (Vide Punjab State Electricity Board Ltd. v. Zora Singh & Ors.,
(2005) 6 SCC 776; and Union of India Through Government of
Pondicherry & Anr. v. V. Ramakrishnan & Ors., (2005) 8 SCC 394).
27. The instant case is required to be examined in the light of the
aforesaid settled legal propositions.
Admittedly, Writ Petition No. 1132 of 2002, wherein the issue of
examining the violation of guidelines issued by the Corporation had been
raised and the High Court had passed certain directions which had been
16
complied with and in pursuance of the same the Corporation passed an order
dated 6.4.2004 that an order passed by it would be subject to the decision in
the said Writ Petition No. 1132 of 2002 is still pending before the High
Court. In such a fact-situation, if the respondent Nos. 1 to 5 were aggrieved
by the order passed by the Corporation they ought to have filed an
application for intervention and appropriate directions in the said writ
petition. Undoubtedly, there could be no prohibition for filing a fresh writ
petition, but it would have been more appropriate for them to file an
application in the said pending writ petition as it is necessary that
contradictory orders must not be passed in similar circumstances.
28. The High Court could not have allowed the Corporation to recall its
earlier order and pass a fresh order, that too, without giving an opportunity
of hearing to the appellant and the Society. Review is a statutory remedy. In
spite of several queries put by us to the learned counsel for the respondents,
no provision for review under the statute could be brought to our notice.
The court cannot confer a jurisdiction upon any authority. Conferring
jurisdiction upon a Court/Tribunal/Authority is a legislative function and
the same cannot be conferred either by the court or by the consent of the
parties. Such an order passed by the High Court is without jurisdiction and,
17
therefore, a nullity. Any order passed in pursuance thereof, also remains
unenforceable and inexecutable. More so, the High Court could not have
permitted the Corporation to pass an order without giving an opportunity of
hearing to the appellant and the society. More so, the Corporation could not
pass an order recalling the order passed by it earlier and reviewing the same
without assigning any reason. It was obligatory on the part of the
Corporation to explain as to what was the material on record on the basis of
which the earlier order has been changed. Thus, the order passed by the
Corporation stood vitiated for not recording reasons and violating the
principles of natural justice. It establishes the allegations of legal malice
made by the appellant against the Corporation.
29. The submission made on behalf of respondent Nos. 1 to 5 that
appellant could not challenge the orders passed by the Corporation directly
before this Court without approaching the High Court is preposterous for the
reason that Corporation passed the impugned orders in pursuance of the
orders passed by the High Court itself. In fact, it could amount to
challenging the basic order passed by the High Court before itself under the
garb of challenging the consequential orders passed by the Corporation.
"The clitch of appeal from Ceasar to Ceasar's wife can only be bettered by
18
appeal from one's own order to oneself." (See Ram and Shyam Company
v. State of Haryana & Ors., AIR 1985 SC 1147).
30. It has been mentioned by the appellant in the petition that respondent
No. 1 himself has vetted the agreement reached between the appellant and
the respondent-society and was a party to the same. Therefore, he was fully
aware as what was the agreement and how it would be given effect to. The
respondent No.1 has not denied this averment. Nor he has explained as to
what were the changed circumstances, which made him aggrieved. More so,
if the said respondent Nos. 1 to 5 were aggrieved of the order passed by the
Co-operative Court rejecting their application of interim relief, they could
have approached the appropriate forum challenging the same, rather they
have chosen to approach the High Court leaving the matter pending before
the Co-operative Court.
31. Respondent No.1 had approached the Co-operative Court and could
not get the interim relief. He filed a writ petition along with others after
meeting his waterloo there. Subsequently, after obtaining the interim orders
from the High Court and consequential orders from the Corporation
withdrew the writ petition.
19
The respondent Nos. 1 to 5 for the reasons best known to them have
prayed for withdrawal of the Writ Petition No. 2366 of 2007 and the High
court vide order dated 13.2.2008 allowed the said respondents to withdraw
the same. The order reads as under:
"As per the statement by Mr. S.U. Kamdar on 4th
February, 2008, the earlier order has been withdrawn by
the corporation and fresh order has been passed by the
concerned officer. The copy of the said order is produced.
It is marked Exhibit-X for identification purpose. Mr. S.U.
Kamdar has further reported to the court that the action of
removal of the hoardings has already been commenced
and it will be completed within two to three days.
In view of the fresh order passed by the corporation
marked Exhibit-X and the statement of Mr. S.U. Kamdar,
learned counsel for the petitioner states that the grievance
in the petition is redressed and, therefore, he may be
allowed to withdraw the petition with liberty to file similar
type of petition if occasion so arises.
Petition is allowed to be withdrawn with liberty as
prayed for."
32. "Withdrawal" means "to go away or retire from the field of battle or
any contest." Thus, the word `withdrawal' is indicative of the voluntary and
conscious decision of a person. Therefore, if the said writ petitioners
(respondent Nos. 1 to 5) have voluntarily abandoned their claim
withdrawing the said writ petition, they cannot be permitted to take any
benefit of the orders passed by the High Court or the statutory authority in
20
pursuance thereof. Once the foundation is removed, the super-structure is
bound to fall. Interim relief is granted only in aid of and as ancillary to the
main relief which may be available to the party at the time of final
adjudication of the case by the court. In case the orders passed by the High
Court and, consequently, by the Corporation are accepted to be in effect
even today, it would be tantamount to allowing the writ petition without any
adjudication on the issues involved therein. After obtaining interim relief, a
party cannot avoid final adjudication of the dispute on merit and claim that
he would enjoy the fruits of interim relief even after withdrawal/dismissal of
the case. Law certainly would not permit such a course. Respondent No.1
is a practising advocate. He is not a layman, nor it can be assumed that he
could not understand the consequences of withdrawal of the writ petition.
Therefore, all orders passed by the High Court and the statutory authority
stood washed away on withdrawal of the said writ petition and the said writ
petitioners cannot claim any benefit of either of the same.
33. In view of the above, appeals deserve to be allowed to the effect that
the appellant and the respondent-Society may act as if no order had ever
been passed, adversely affecting their contract, by the High Court in Writ
21
Petition No.2366 of 2007 or any statutory authority and they may proceed
with the agreement/contract in accordance with law.
34. Needless to say that this judgment/order would have no bearing on the
order passed by any court/tribunal or statutory authority independent of the
proceedings taken in Writ Petition No. 2366 of 2007.
35. The appeals are allowed as explained hereinabove. No order as to
cost.
............................J.
(P.
SATHASIVAM)
............................J.
New Delhi, (Dr. B.S. CHAUHAN)
September 6, 2010
22
23
FREE Legal advice service Help! We offer a comprehensive legal advice and opinion service covering all aspects of Indian law: Email a legal question. WE DO NOT ASK ANY INFORMATION FROM USERS
Home | Contact | Supreme Court | Law | M.V Act | Negotiable Instruments Act | Criminal | Civil | Disclaimer |
RSS | Comments RSS
Wednesday, September 8, 2010
Kalabharati Advertising V/s Hemant Vimalnath Narichania SLP (C) Nos.25043-25045 of 2008 September 6, 2010
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment